Lime Lane, Pelsall (100 MW battery storage)

Lime Lane, Pelsall is a 100 MW battery storage project in Cannock Chase, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 28 May 2026; the record was last updated on 23 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
refusedstatus in REPD
23 June 2026record last updated
Cannock Chasecouncil area

Planning timeline

DateStage
23 July 2025Application submitted
28 May 2026Refused by the planning authority

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
refused
Record last updated
23 June 2026
Operator or applicant
Elgin Energy Esco Limited
Planning authority
Cannock Chase
Planning application reference
CH/25/0225
Address (REPD)
The rear of the Bungalow, Lime Lane, Pelsall
Council area (by location)
Cannock Chase
Time to decision
44 weeks
Name in REPD
Lime Lane, Pelsall - Battery Energy Storage System
REPD reference
19451

Who decides

Cannock Chase has 1 decided solar, wind or battery application in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Other large projects within 10 km

ProjectTypeMWStatuskm
Hobble Lane, Great Wyrleybattery storage49.9approved, not built2.8
Bleak Housewind farm6.5application withdrawn4.3
Lions Den, Hammerwichbattery storage100approved, not built5.2
Bognop Road, Essington Solar Farm & Battery Energy Storagesolar farm35application submitted6.6
Bloxwich Batterybattery storage41operational8.0
New Road, Featherstonebattery storage100application withdrawn8.1
Upper Latherford Farm, Latherford Lanebattery storage50approved, not built8.2
Oaklands Farm, New Roadbattery storage70approved, not built9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6582, -1.9738).