Energy Projects Near You

Lions Den, Hammerwich (100 MW battery storage)

Lions Den, Hammerwich is a 100 MW battery storage project in Lichfield, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 24 July 2025, not yet built; the record was last updated on 5 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
approved, not builtstatus in REPD
5 August 2025record last updated
Lichfieldcouncil area

Planning timeline

DateStage
19 December 2024Application submitted
24 July 2025Planning permission granted
24 July 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
approved, not built
Record last updated
5 August 2025
Operator or applicant
Elgin Energy Services Limited
Planning authority
Lichfield
Planning application reference
24/01169/FULM
Address (REPD)
N/O A5 Lions Den, Hammerwich, Burntwood
Council area (by location)
Lichfield
Time to decision
31 weeks
Name in REPD
Lions Den, Hammerwich - Battery Storage Facility
REPD reference
14418

Who decides

ApplicationsLichfieldUK
Decided applications (solar, wind, battery)1310,236
Refused2 (15%)19%
Solar refused0 of 1012%
Onshore wind refused1 of 145%
Battery storage refused1 of 216%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lime Lane, Pelsallbattery storage100refused5.2
Bleak Housewind farm6.5application withdrawn5.4
Hobble Lane, Great Wyrleybattery storage49.9approved, not built7.8
Hawkesyard Estate, Rugeley Roadbattery storage100application submitted8.8
Armitage Road, Armitagebattery storage200refused9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6656, -1.898).