Energy Projects Near You

Solar, wind and battery projects near Lichfield (WS14)

13 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of WS14 (Lichfield): 2 are waiting for a planning decision, 8 approved but not yet running, 2 operational. The largest live scheme is Lions Den, Hammerwich (100 MW battery storage, approved on 24 July 2025, not yet built), 5.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13projects within 10 km
2awaiting a decision
8approved, not running
2operational

Projects within 10 km of WS14

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Huddlesford Farmsolar farmsolar farm1operationalupdated Jul 2018Jun 2014granted Oct 2014Jul 2018Lichfield3.5
Park Lanesolar farmsolar farm1operationalupdated Jul 2018Jun 2014granted Nov 2014Jul 2018Lichfield4.1
Lions Den, Hammerwichbattery storagebattery storage100approved, not builtupdated Aug 2025Dec 2024granted Jul 2025Aug 2025Lichfield5.5
Smaller schemes under 1 MW, mostly rooftop solar (10)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
David Lloyd Clubs, Birmingham Roadrooftop solarrooftop solar—application submittedupdated Aug 2025Jul 2025—Aug 2025Lichfield1.8
The Food Warehouse by Icelandrooftop solarrooftop solar0.1approved, not builtupdated Apr 2026Jan 2026granted Feb 2026Apr 2026Lichfield3.2
Wood End Lane, Fradley - Micro Energy Storagebattery storagebattery storage0.2application submittedJun 2026——Lichfield5.3
Newell Rubbermaid, Halifax Avenuerooftop solarrooftop solar0.6approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Lichfield5.8
Rawlett Community Sports Collegerooftop solarrooftop solar0.2application withdrawnupdated Sep 2021Feb 2021—Sep 2021Tamworth7.9
Little Aston Hospital, Little Aston Hall Driverooftop solarrooftop solar0.2approved, not builtupdated May 2024Mar 2024granted May 2024May 2024Lichfield8.2
Steel Processing Midlands, Burntwood Business Parkrooftop solarrooftop solar0.2approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Lichfield8.3
J Sainsbury, Elmhurst Driverooftop solarrooftop solar0.5approved, not builtupdated Dec 2023Oct 2023granted Nov 2023Dec 2023Tamworth8.5
Landau Forte Academy Qemsrooftop solarrooftop solar0.4approved, not builtupdated Jul 2024Apr 2024granted Jun 2024Jul 2024Tamworth8.8
Erdington Road, Aldridgerooftop solarrooftop solar0.3approved, not builtupdated May 2022Apr 2022granted May 2022May 2022Walsall9.8

Distance from the average position of the WS14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm200200
Rooftop solar917002.4
Battery storage21100100

MW in pipeline: pending, approved and under-construction capacity.

How Lichfield decides solar, wind and battery applications

ApplicationsLichfieldUK
Decided applications (solar, wind, battery)1310,236
Refused2 (15%)19%
Solar refused0 of 1012%
Onshore wind refused1 of 145%
Battery storage refused1 of 216%
Median time from submission to decision24.7 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Lichfield

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.