Energy Projects Near You

Solar, wind and battery projects near Stafford (ST20)

9 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of ST20 (Stafford): 3 are waiting for a planning decision, 1 approved but not yet running. The largest live scheme is Flashbrook Road, Knighton Solar Farm (49.9 MW solar farm, application submitted on 29 February 2024, no decision recorded; REPD status may be out of date), 8.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9projects within 10 km
3awaiting a decision
1approved, not running
0operational

Projects within 10 km of ST20

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Knightley Hall Wind Farmwind farmwind farm6refusedupdated Feb 2015Jun 2014refused Jan 2015Feb 2015Stafford0.6
Wincote Farm, Wincote Lane Solar Farmsolar farmsolar farm30.2application submitted may be out of dateupdated May 2023Mar 2023—May 2023Stafford5.1
Tunstall Hall Farmsolar farmsolar farm5refusedupdated Jan 2016Sep 2015refused Dec 2015Jan 2016Stafford5.6
King's Streetwind farmwind farm12refusedupdated Aug 2011Dec 2010refused Apr 2011Aug 2011South Staffordshire7.3
Flashbrook Road, Knighton Solar Farmsolar farmsolar farm49.9application submitted may be out of dateupdated Mar 2024Feb 2024—Mar 2024Stafford8.9
Flashbrook Road, Knighton Solar Farmbattery storagebattery storage15application submitted may be out of dateupdated Mar 2024Feb 2024—Mar 2024Stafford8.9
Unit DC 1 - Screwfix Directrooftop solarrooftop solar1.8application withdrawnupdated Dec 2015Sep 2015—Dec 2015Stafford10.0
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Fernhill Farm, Fernhill Roadsolar farmsolar farm0.2approved, not builtupdated Sep 2024Jun 2024granted Sep 2024Sep 2024Stafford5.0
Victoria Park Energy Storage Facilitybattery storagebattery storage0.2application withdrawnupdated Feb 2025Nov 2024—Feb 2025Telford and Wrekin7.3

Distance from the average position of the ST20 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm4210180.4
Rooftop solar100000
Wind farm200020
Battery storage2100015

MW in pipeline: pending, approved and under-construction capacity.

How Stafford decides solar, wind and battery applications

ApplicationsStaffordUK
Decided applications (solar, wind, battery)2010,236
Refused5 (25%)19%
Solar refused3 of 1412%
Onshore wind refused1 of 145%
Battery storage refused1 of 516%
Median time from submission to decision16.3 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

All projects in Stafford

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near ST20, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.