Solar, wind and battery projects near Stafford (ST21)
14 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of ST21 (Stafford): 4 are waiting for a planning decision, 6 approved but not yet running. The largest live scheme is Flashbrook Road, Knighton Solar Farm (49.9 MW solar farm, application submitted on 29 February 2024, no decision recorded; REPD status may be out of date), 7.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of ST21
Projects of 1 MW and more (9)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Aspley House Farm, Aspley Lanebattery storage | battery storage | 10 | approved, not built may be out of dateupdated Feb 2023 | Oct 2022 | granted Jan 2023 | Feb 2023 | Stafford | 2.5 |
| Wincote Farm, Wincote Lane Solar Farmsolar farm | solar farm | 30.2 | application submitted may be out of dateupdated May 2023 | Mar 2023 | — | May 2023 | Stafford | 3.2 |
| Tunstall Hall Farmsolar farm | solar farm | 5 | refusedupdated Jan 2016 | Sep 2015 | refused Dec 2015 | Jan 2016 | Stafford | 4.3 |
| Newcastle Road, Cotes Heathsolar farm | solar farm | 15 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Stafford | 4.5 |
| Flashbrook Road, Knighton Solar Farmsolar farm | solar farm | 49.9 | application submitted may be out of dateupdated Mar 2024 | Feb 2024 | — | Mar 2024 | Stafford | 7.7 |
| Flashbrook Road, Knighton Solar Farmbattery storage | battery storage | 15 | application submitted may be out of dateupdated Mar 2024 | Feb 2024 | — | Mar 2024 | Stafford | 7.7 |
| Knightley Hall Wind Farmwind farm | wind farm | 6 | refusedupdated Feb 2015 | Jun 2014 | refused Jan 2015 | Feb 2015 | Stafford | 7.9 |
| Unit DC 1 - Screwfix Directrooftop solar | rooftop solar | 1.8 | application withdrawnupdated Dec 2015 | Sep 2015 | — | Dec 2015 | Stafford | 9.7 |
| Malthouse Solar Farmsolar farm | solar farm | 5 | refusedupdated Dec 2015 | Jul 2015 | refused Nov 2015 | Dec 2015 | Stafford | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (5)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Brooms Road - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated May 2026 | Oct 2025 | granted Mar 2026 | May 2026 | Stafford | 8.8 |
| Cheswardine Hall Residential Homesolar farm | solar farm | 0.2 | approved, not builtupdated Mar 2024 | Nov 2023 | granted Mar 2024 | Mar 2024 | Shropshire | 9.5 |
| Barlastonbattery storage | battery storage | — | approved, not built may be out of dateupdated Apr 2022 | Dec 2021 | granted Oct 2022 | Apr 2022 | Stafford | 9.5 |
| Pets at Home Distribution Centre, Stone Roadrooftop solar | rooftop solar | 0.9 | approved, not builtupdated Jan 2024 | Nov 2023 | granted Dec 2023 | Jan 2024 | Stafford | 9.7 |
| Aston Marina, Lichfield Roadsolar farm | solar farm | 0.3 | approved, not builtupdated Jan 2025 | Apr 2024 | granted Dec 2024 | Jan 2025 | Stafford | 9.9 |
Distance from the average position of the ST21 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 7 | 3 | 2 | 0 | 2 | 95.7 |
| Rooftop solar | 2 | 0 | 1 | 0 | 0 | 0.9 |
| Wind farm | 1 | 0 | 0 | 0 | 1 | 0 |
| Battery storage | 4 | 1 | 3 | 0 | 0 | 25.2 |
MW in pipeline: pending, approved and under-construction capacity.
How Stafford decides solar, wind and battery applications
| Applications | Stafford | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 20 | 10,236 |
| Refused | 5 (25%) | 19% |
| Solar refused | 3 of 14 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 1 of 5 | 16% |
| Median time from submission to decision | 16.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 2 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near ST21, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.