Energy Projects Near You

Solar, wind and battery projects near Market Drayton (TF9)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TF9 (Shropshire): 2 are waiting for a planning decision, 4 approved but not yet running. The largest live scheme is Flashbrook Road, Knighton Solar Farm (49.9 MW solar farm, application submitted on 29 February 2024, no decision recorded; REPD status may be out of date), 8.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
2awaiting a decision
4approved, not running
0operational

Projects within 10 km of TF9

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hollins Lanebattery storagebattery storage13approved, not built may be out of dateupdated May 2023Jan 2023granted May 2023May 2023Shropshire1.9
Poplar Lane Wind Farmwind farmwind farm14refused on appealupdated Dec 2010Apr 2008refused Sep 2008Dec 2010Shropshire7.6
Flashbrook Road, Knighton Solar Farmsolar farmsolar farm49.9application submitted may be out of dateupdated Mar 2024Feb 2024—Mar 2024Stafford8.1
Flashbrook Road, Knighton Solar Farmbattery storagebattery storage15application submitted may be out of dateupdated Mar 2024Feb 2024—Mar 2024Stafford8.1
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Merlot Chitty Farms, Bettonrooftop solarrooftop solar0.3approved, not builtupdated Sep 2025Aug 2025granted Sep 2025Sep 2025Shropshire3.7
Cheswardine Hall Residential Homesolar farmsolar farm0.2approved, not builtupdated Mar 2024Nov 2023granted Mar 2024Mar 2024Shropshire4.6
TB Electrics, Sandfordrooftop solarrooftop solar0.2approved, not builtupdated Sep 2025Jul 2025granted Aug 2025Sep 2025Shropshire8.5

Distance from the average position of the TF9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm2110050.1
Rooftop solar202000.5
Wind farm100010
Battery storage2110028

MW in pipeline: pending, approved and under-construction capacity.

How Shropshire decides solar, wind and battery applications

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

All projects in Shropshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TF9, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.