Solar, wind and battery projects near Newcastle-under-Lyme (ST55)
41 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of ST55 (Newcastle-under-Lyme): 2 are waiting for a planning decision, 30 approved but not yet running, 5 operational. The largest live scheme is Armshead Farm, Armshead Road (50 MW battery storage, approved on 23 September 2024, not yet built), 9.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of ST55
Projects of 1 MW and more (12)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Noriker Power Staunchbattery storage | battery storage | 20 | operationalupdated May 2019 | Mar 2016 | granted May 2016 | May 2019 | Newcastle-under-Lyme | 2.1 |
| Royal Stoke University Hospitalrooftop solar | rooftop solar | 1 | approved, not builtupdated Nov 2025 | Aug 2025 | granted Sep 2025 | Nov 2025 | Stoke-on-Trent | 2.1 |
| Rubber and Allied Productsbattery storage | battery storage | 40 | approved, not built may be out of dateupdated Apr 2020 | Oct 2017 | granted Dec 2017 | Apr 2020 | Newcastle-under-Lyme | 2.3 |
| Keele Universitysolar farm | solar farm | 4.4 | operationalupdated May 2022 | Dec 2018 | granted Feb 2019 | May 2022 | Newcastle-under-Lyme | 2.5 |
| The Low Carbon Energy Generation Project at Keele Universitywind farm | wind farm | 1.9 | operationalupdated Sep 2021 | Dec 2018 | granted May 2019 | Sep 2021 | Newcastle-under-Lyme | 2.6 |
| Leek Roadsolar farm | solar farm | 1.1 | approved, not built may be out of dateupdated Dec 2021 | Nov 2021 | granted Jan 2022 | Dec 2021 | Stoke-on-Trent | 5.3 |
| Screwfix Directrooftop solar | rooftop solar | 2.5 | operationalupdated Sep 2016 | Oct 2015 | granted Nov 2015 | Sep 2016 | Stoke-on-Trent | 6.2 |
| Brown Edgebattery storage | battery storage | 49.5 | approved, not builtupdated May 2025 | Mar 2022 | granted May 2025 | May 2025 | Stoke-on-Trent | 8.6 |
| Maer Hills Wind Farmwind farm | wind farm | 8 | abandonedupdated Sep 2011 | Jun 2008 | granted Feb 2009 | Sep 2011 | Newcastle-under-Lyme | 9.3 |
| Malthouse Solar Farmsolar farm | solar farm | 5 | refusedupdated Dec 2015 | Jul 2015 | refused Nov 2015 | Dec 2015 | Stafford | 9.5 |
| Armshead Farm, Armshead Roadbattery storage | battery storage | 50 | approved, not builtupdated Oct 2024 | Nov 2022 | refused Jun 2023 | Oct 2024 | Staffordshire Moorlands | 9.7 |
| Adj New House Farm, Luzlow Lanebattery storage | battery storage | 99 | refusedupdated Jan 2026 | Feb 2025 | refused Dec 2025 | Jan 2026 | Staffordshire Moorlands | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (29)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Workshop, Croft Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Mar 2025 | granted Apr 2025 | May 2025 | Newcastle-under-Lyme | 0.9 |
| Coaldale Road & Ore Close, Lymedale Business Park - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | Newcastle-under-Lyme | 1.6 |
| Tree Of Life, Coaldale Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jun 2023 | Apr 2023 | granted May 2023 | Jun 2023 | Newcastle-under-Lyme | 1.7 |
| Arnold Clark Automobiles Limited, Brymbo Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | Newcastle-under-Lyme | 1.8 |
| Hamptons Industrial Estatebattery storage | battery storage | — | application submittedupdated Mar 2026 | Feb 2026 | — | Mar 2026 | Newcastle-under-Lyme | 2.2 |
| The 4 Candles, High Streetrooftop solar | rooftop solar | — | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Newcastle-under-Lyme | 2.4 |
| The 4 Candles, High Streetbattery storage | battery storage | — | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Newcastle-under-Lyme | 2.4 |
| Keele Universitybattery storage | battery storage | — | operationalupdated May 2022 | Dec 2018 | granted Sep 2019 | May 2022 | Newcastle-under-Lyme | 2.5 |
| Manor Bakeries, Newcastle Road Solar Photovoltaics Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Dec 2023 | Dec 2023 | Stoke-on-Trent | 2.7 |
| Manor Bakeries, Newcastle Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Nov 2024 | Sep 2024 | granted Nov 2024 | Nov 2024 | Stoke-on-Trent | 2.8 |
| Bradwell Hospital,Talke Roadrooftop solar | rooftop solar | — | approved, not builtupdated May 2025 | Mar 2025 | granted Apr 2025 | May 2025 | Newcastle-under-Lyme | 2.8 |
| Thistley Hough Academy, Thistley Houghrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Stoke-on-Trent | 2.9 |
| Arnold Clark Automobilesrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2026 | Dec 2025 | granted Feb 2026 | Mar 2026 | Stoke-on-Trent | 3.4 |
| Advanced Packaging, Rosevale Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Aug 2025 | Sep 2025 | Newcastle-under-Lyme | 3.4 |
| Bradwell Hall Nursing Home, Old Hall Driverooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jan 2023 | Nov 2022 | granted Jan 2023 | Jan 2023 | Newcastle-under-Lyme | 3.4 |
| Central Food, Unicorn Industrial Estaterooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2023 | Mar 2023 | granted Apr 2023 | May 2023 | Stoke-on-Trent | 3.9 |
| Forfarmers, Speedwell Road- Solar Panelsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jul 2023 | May 2023 | granted Jun 2023 | Jul 2023 | Newcastle-under-Lyme | 4.1 |
| James T Blakeman Services, High Carr Business Parkrooftop solar | rooftop solar | 0.7 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | Newcastle-under-Lyme | 4.5 |
| Tunstall Trade Park, Brownhills Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 | Stoke-on-Trent | 4.7 |
| Armadillo Self Storage, Victoria Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2025 | May 2025 | granted Aug 2025 | Sep 2025 | Stoke-on-Trent | 4.9 |
| Haywood Hospital, High Lane Solar Canopyrooftop solar | rooftop solar | — | approved, not builtupdated Nov 2025 | Mar 2025 | granted May 2025 | Nov 2025 | Stoke-on-Trent | 5.7 |
| Churchill China Uk Limited, Marlborough Way, Sandyfordrooftop solar | rooftop solar | 1 | approved, not builtupdated Dec 2021 | Nov 2021 | granted Jan 2022 | Dec 2021 | Stoke-on-Trent | 6.1 |
| Churchill China Uk Limited, Marlborough Way, Sandyfordrooftop solar | rooftop solar | 0.8 | refusedupdated Mar 2022 | Jan 2022 | refused Mar 2022 | Mar 2022 | Stoke-on-Trent | 6.1 |
| Churchill China Uk Limited, Marlborough Way, Sandyfordrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2022 | Mar 2022 | granted Apr 2022 | Mar 2022 | Stoke-on-Trent | 6.1 |
| Marlborough Works, High Streetrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jun 2022 | May 2022 | granted Jun 2022 | Jun 2022 | Stoke-on-Trent | 6.1 |
| Ford Green Trade Centre, Ford Green Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2026 | Sep 2025 | granted Oct 2025 | Jan 2026 | Stoke-on-Trent | 6.5 |
| Mossfield Road Solar PV Generation Systemrooftop solar | rooftop solar | 0.4 | approved, not built may be out of dateupdated Dec 2021 | Nov 2021 | granted Jan 2022 | Dec 2021 | Stoke-on-Trent | 7.3 |
| Cromartie Hobbycraft, From Park Hall Road - Micro Energy Storagebattery storage | battery storage | 0.2 | application submitted | Feb 2026 | — | — | Stoke-on-Trent | 8.4 |
| Ormiston Meridian Academy, Sandon Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | Stoke-on-Trent | 9.9 |
Distance from the average position of the ST55 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 3 | 0 | 1 | 1 | 1 | 1.1 |
| Rooftop solar | 26 | 0 | 24 | 1 | 1 | 8 |
| Wind farm | 2 | 0 | 0 | 1 | 0 | 0 |
| Battery storage | 10 | 2 | 5 | 2 | 1 | 140 |
MW in pipeline: pending, approved and under-construction capacity.
How Newcastle-under-Lyme decides solar, wind and battery applications
| Applications | Newcastle-under-Lyme | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 17 | 10,236 |
| Refused | 0 (0%) | 19% |
| Solar refused | 0 of 10 | 12% |
| Onshore wind refused | 0 of 2 | 45% |
| Battery storage refused | 0 of 5 | 16% |
| Median time from submission to decision | 8.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
All projects in Newcastle-under-Lyme
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near ST55, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.