Adj New House Farm, Luzlow Lane (99 MW battery storage)

Adj New House Farm, Luzlow Lane is a 99 MW battery storage project in Staffordshire Moorlands, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 12 December 2025; the record was last updated on 26 January 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

99 MWbattery storage
refusedstatus in REPD
26 January 2026record last updated
Staffordshire Moorlandscouncil area

Planning timeline

DateStage
18 February 2025Application submitted
12 December 2025Refused by the planning authority

Project details

Technology
battery storage (stand-alone storage)
Capacity
99 MW
Status (REPD)
refused
Record last updated
26 January 2026
Operator or applicant
YLEM (BESS) South Limited
Planning authority
Staffordshire Moorlands
Planning application reference
SMD/2024/0568
Address (REPD)
Adjoining, New House Farm, Luzlow Lane, Bagnall
Council area (by location)
Staffordshire Moorlands
Time to decision
42 weeks
Name in REPD
Adj New House Farm, Luzlow Lane - Battery Energy Storage
REPD reference
16521

Who decides

ApplicationsStaffordshire MoorlandsUK
Decided applications (solar, wind, battery)2510,236
Refused8 (32%)19%
Solar refused3 of 1512%
Battery storage refused5 of 1016%
Median time from submission to decision28.4 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Armshead Farm, Armshead Roadbattery storage50approved, not built0.9
Cellarhead Substation, Rownall Roadbattery storage400application submitted1.2
Cellarhead Substation, Rownall Road Battery Energy Facilitybattery storage400approved, not built1.3
Newfields Farm, Rownall Roadbattery storage99.9approved, not built1.6
Leek Road, Werringtonbattery storage300application submitted2.8
Land at Heywood Grangesolar farm8.4operational5.5
Brown Edgebattery storage49.5approved, not built5.7
The Fields Farmsolar farm5refused9.0
Draycott Cross Roadbattery storage40approved, not built9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.0409, -2.0969).