Solar, wind and battery projects near Stoke-on-Trent (ST9)
39 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of ST9 (Staffordshire Moorlands): 5 are waiting for a planning decision, 30 approved but not yet running, 2 operational. The largest live scheme is Cellarhead Substation, Rownall Road Battery Energy Facility (400 MW battery storage, approved on 22 December 2022, not yet built; REPD status may be out of date), 1.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of ST9
Projects of 1 MW and more (12)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Adj New House Farm, Luzlow Lanebattery storage | battery storage | 99 | refusedupdated Jan 2026 | Feb 2025 | refused Dec 2025 | Jan 2026 | Staffordshire Moorlands | 1.3 |
| Newfields Farm, Rownall Roadbattery storage | battery storage | 99.9 | approved, not builtupdated Jul 2025 | Jan 2025 | granted Jul 2025 | Jul 2025 | Staffordshire Moorlands | 1.5 |
| Cellarhead Substation, Rownall Road Battery Energy Facilitybattery storage | battery storage | 400 | approved, not built may be out of dateupdated Jan 2023 | Aug 2022 | granted Dec 2022 | Jan 2023 | Staffordshire Moorlands | 1.6 |
| Cellarhead Substation, Rownall Roadbattery storage | battery storage | 2.6 | application submitted may be out of dateupdated Oct 2022 | Oct 2022 | — | Oct 2022 | Staffordshire Moorlands | 1.7 |
| Cellarhead Substation, Rownall Roadbattery storage | battery storage | 400 | application submitted may be out of dateupdated Apr 2024 | Feb 2024 | — | Apr 2024 | Staffordshire Moorlands | 2.0 |
| Armshead Farm, Armshead Roadbattery storage | battery storage | 50 | approved, not builtupdated Oct 2024 | Nov 2022 | refused Jun 2023 | Oct 2024 | Staffordshire Moorlands | 2.2 |
| Leek Road, Werringtonbattery storage | battery storage | 300 | application submittedupdated Sep 2025 | Aug 2025 | — | Sep 2025 | Staffordshire Moorlands | 3.8 |
| Brown Edgebattery storage | battery storage | 49.5 | approved, not builtupdated May 2025 | Mar 2022 | granted May 2025 | May 2025 | Stoke-on-Trent | 5.0 |
| Leek Roadsolar farm | solar farm | 1.1 | approved, not built may be out of dateupdated Dec 2021 | Nov 2021 | granted Jan 2022 | Dec 2021 | Stoke-on-Trent | 5.5 |
| Land at Heywood Grangesolar farm | solar farm | 8.4 | operationalupdated Dec 2016 | Feb 2015 | granted Sep 2015 | Dec 2016 | Staffordshire Moorlands | 6.6 |
| Royal Stoke University Hospitalrooftop solar | rooftop solar | 1 | approved, not builtupdated Nov 2025 | Aug 2025 | granted Sep 2025 | Nov 2025 | Stoke-on-Trent | 9.5 |
| Screwfix Directrooftop solar | rooftop solar | 2.5 | operationalupdated Sep 2016 | Oct 2015 | granted Nov 2015 | Sep 2016 | Stoke-on-Trent | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (27)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Greenfields Farm, Thorney Edge Roadbattery storage | battery storage | — | application submittedupdated Oct 2024 | Oct 2024 | — | Oct 2024 | Staffordshire Moorlands | 1.1 |
| F Ball & Company Limited, Station Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jan 2024 | Oct 2023 | granted Dec 2023 | Jan 2024 | Staffordshire Moorlands | 4.7 |
| Ford Green Trade Centre, Ford Green Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2026 | Sep 2025 | granted Oct 2025 | Jan 2026 | Stoke-on-Trent | 4.8 |
| Consall Hall Gardenssolar farm | solar farm | 0.3 | approved, not builtupdated Nov 2025 | Feb 2024 | granted Apr 2025 | Nov 2025 | Staffordshire Moorlands | 5.6 |
| Mossfield Road Solar PV Generation Systemrooftop solar | rooftop solar | 0.4 | approved, not built may be out of dateupdated Dec 2021 | Nov 2021 | granted Jan 2022 | Dec 2021 | Stoke-on-Trent | 5.9 |
| Cromartie Hobbycraft, From Park Hall Road - Micro Energy Storagebattery storage | battery storage | 0.2 | application submitted | Feb 2026 | — | — | Stoke-on-Trent | 6.3 |
| Haywood Hospital, High Lane Solar Canopyrooftop solar | rooftop solar | — | approved, not builtupdated Nov 2025 | Mar 2025 | granted May 2025 | Nov 2025 | Stoke-on-Trent | 6.4 |
| Armadillo Self Storage, Victoria Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2025 | May 2025 | granted Aug 2025 | Sep 2025 | Stoke-on-Trent | 6.6 |
| Arnold Clark Automobilesrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2026 | Dec 2025 | granted Feb 2026 | Mar 2026 | Stoke-on-Trent | 7.1 |
| Tunstall Trade Park, Brownhills Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 | Stoke-on-Trent | 7.6 |
| Central Food, Unicorn Industrial Estaterooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2023 | Mar 2023 | granted Apr 2023 | May 2023 | Stoke-on-Trent | 7.8 |
| The 4 Candles, High Streetrooftop solar | rooftop solar | — | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Newcastle-under-Lyme | 8.5 |
| The 4 Candles, High Streetbattery storage | battery storage | — | approved, not builtupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | Newcastle-under-Lyme | 8.5 |
| Churchill China Uk Limited, Marlborough Way, Sandyfordrooftop solar | rooftop solar | 1 | approved, not builtupdated Dec 2021 | Nov 2021 | granted Jan 2022 | Dec 2021 | Stoke-on-Trent | 8.6 |
| Churchill China Uk Limited, Marlborough Way, Sandyfordrooftop solar | rooftop solar | 0.8 | refusedupdated Mar 2022 | Jan 2022 | refused Mar 2022 | Mar 2022 | Stoke-on-Trent | 8.6 |
| Churchill China Uk Limited, Marlborough Way, Sandyfordrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2022 | Mar 2022 | granted Apr 2022 | Mar 2022 | Stoke-on-Trent | 8.6 |
| Marlborough Works, High Streetrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jun 2022 | May 2022 | granted Jun 2022 | Jun 2022 | Stoke-on-Trent | 8.6 |
| Ormiston Meridian Academy, Sandon Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | Stoke-on-Trent | 8.9 |
| VWS, Meirrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2025 | Feb 2025 | granted Mar 2025 | Mar 2025 | Stoke-on-Trent | 9.0 |
| Unit 2, G-park, Whittle Roadrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Jun 2022 | Jun 2022 | granted Aug 2022 | Jun 2022 | Stoke-on-Trent | 9.1 |
| Thistley Hough Academy, Thistley Houghrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Stoke-on-Trent | 9.3 |
| Bradwell Hall Nursing Home, Old Hall Driverooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jan 2023 | Nov 2022 | granted Jan 2023 | Jan 2023 | Newcastle-under-Lyme | 9.5 |
| Workshop, Croft Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2025 | Mar 2025 | granted Apr 2025 | May 2025 | Newcastle-under-Lyme | 9.6 |
| Bradwell Hospital,Talke Roadrooftop solar | rooftop solar | — | approved, not builtupdated May 2025 | Mar 2025 | granted Apr 2025 | May 2025 | Newcastle-under-Lyme | 9.7 |
| Forfarmers, Speedwell Road- Solar Panelsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jul 2023 | May 2023 | granted Jun 2023 | Jul 2023 | Newcastle-under-Lyme | 9.8 |
| James T Blakeman Services, High Carr Business Parkrooftop solar | rooftop solar | 0.7 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | Newcastle-under-Lyme | 9.8 |
| Manor Bakeries, Newcastle Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Nov 2024 | Sep 2024 | granted Nov 2024 | Nov 2024 | Stoke-on-Trent | 10.0 |
Distance from the average position of the ST9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 3 | 0 | 2 | 1 | 0 | 1.4 |
| Rooftop solar | 25 | 0 | 23 | 1 | 1 | 8.4 |
| Battery storage | 11 | 5 | 5 | 0 | 1 | 1,302 |
MW in pipeline: pending, approved and under-construction capacity.
How Staffordshire Moorlands decides solar, wind and battery applications
| Applications | Staffordshire Moorlands | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 25 | 10,236 |
| Refused | 8 (32%) | 19% |
| Solar refused | 3 of 15 | 12% |
| Battery storage refused | 5 of 10 | 16% |
| Median time from submission to decision | 28.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 1 | — |
All projects in Staffordshire Moorlands
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near ST9, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.