Energy Projects Near You

Cellarhead Substation, Rownall Road (400 MW battery storage)

Cellarhead Substation, Rownall Road is a 400 MW battery storage project in Staffordshire Moorlands, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 13 February 2024, no decision recorded; the record was last updated on 2 April 2024. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

400 MWbattery storage
application submittedmay be out of datestatus in REPD
2 April 2024record last updated
Staffordshire Moorlandscouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
13 February 2024Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
400 MW
Status (REPD)
application submitted
Record last updated
2 April 2024
Operator or applicant
S & C Energy Limited
Planning authority
Staffordshire Moorlands
Planning application reference
SMD/2024/0055
Address (REPD)
SOUTH OF CELLARHEAD SUBSTATION AND WEST OF, Rownall Road, Wetley Rocks, Staffordshir
Council area (by location)
Staffordshire Moorlands
Name in REPD
Cellarhead Substation, Rownall Road - Battery Storage Facility
REPD reference
16111

Who decides

ApplicationsStaffordshire MoorlandsUK
Decided applications (solar, wind, battery)2510,236
Refused8 (32%)19%
Solar refused3 of 1512%
Battery storage refused5 of 1016%
Median time from submission to decision28.4 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cellarhead Substation, Rownall Road Battery Energy Facilitybattery storage400approved, not built0.7
Adj New House Farm, Luzlow Lanebattery storage99refused1.2
Armshead Farm, Armshead Roadbattery storage50approved, not built1.2
Newfields Farm, Rownall Roadbattery storage99.9approved, not built1.2
Leek Road, Werringtonbattery storage300application submitted1.8
Land at Heywood Grangesolar farm8.4operational4.7
Brown Edgebattery storage49.5approved, not built6.8
Draycott Cross Roadbattery storage40approved, not built8.0
The Fields Farmsolar farm5refused8.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.0372, -2.0806).