Cellarhead Substation, Rownall Road Battery Energy Facility (400 MW)

Cellarhead Substation, Rownall Road Battery Energy Facility is a 400 MW battery storage project in Staffordshire Moorlands, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 22 December 2022, not yet built; the record was last updated on 3 January 2023. REPD also records that the planning permission expired on 22 December 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

400 MWbattery storage
approved, not builtmay be out of datestatus in REPD
3 January 2023record last updated
Staffordshire Moorlandscouncil area

REPD also records that the planning permission expired on 22 December 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
22 August 2022Application submitted
22 December 2022Planning permission granted
22 December 2025Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
400 MW
Status (REPD)
approved, not built
Record last updated
3 January 2023
Operator or applicant
C&S Energy Limited
Planning authority
Staffordshire Moorlands
Planning application reference
SMD/2022/0444
Address (REPD)
East of Cellarhead Substation, and West of Rownall Road, Wetley Rocks
Council area (by location)
Staffordshire Moorlands
Time to decision
17 weeks
Name in REPD
Cellarhead Substation, Rownall Road - Battery Energy Facility
REPD reference
12179

Earlier applications for this site

ApplicationMWSubmittedOutcome
Cellarhead Battery Site SMD/2021/06953493 November 2021refused 21 June 2022

Who decides

ApplicationsStaffordshire MoorlandsUK
Decided applications (solar, wind, battery)2510,236
Refused8 (32%)19%
Solar refused3 of 1512%
Battery storage refused5 of 1016%
Median time from submission to decision28.4 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Newfields Farm, Rownall Roadbattery storage99.9approved, not built0.5
Cellarhead Substation, Rownall Roadbattery storage400application submitted0.7
Adj New House Farm, Luzlow Lanebattery storage99refused1.3
Armshead Farm, Armshead Roadbattery storage50approved, not built1.8
Leek Road, Werringtonbattery storage300application submitted2.3
Land at Heywood Grangesolar farm8.4operational5.3
Brown Edgebattery storage49.5approved, not built6.6
Draycott Cross Roadbattery storage40approved, not built8.5
The Fields Farmsolar farm5refused8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.0431, -2.0775).