Energy Projects Near You

Renewable energy projects in Staffordshire Moorlands

25 solar, wind or battery projects of 150 kW or more are located in Staffordshire Moorlands (REPD, July 2026 extract): 6 pending, 14 approved but not running, 3 operational and 2 refused. The council refused 8 of 25 decided applications (32%; UK 19%), with a median 28 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25projects in the council area
6awaiting a decision
14approved, not running
32%of decisions refused

How Staffordshire Moorlands decides

ApplicationsStaffordshire MoorlandsUK
Decided applications (solar, wind, battery)2510,236
Refused8 (32%)19%
Solar refused3 of 1512%
Battery storage refused5 of 1016%
Median time from submission to decision28.4 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Projects in Staffordshire Moorlands

Projects of 1 MW and more (19)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Cellarhead Substation, Rownall Road Battery Energy Facilitybattery storagebattery storage400approved, not built may be out of dateupdated Jan 2023Aug 2022granted Dec 2022Jan 2023
Cellarhead Substation, Rownall Roadbattery storagebattery storage400application submitted may be out of dateupdated Apr 2024Feb 2024—Apr 2024
Leek Road, Werringtonbattery storagebattery storage300application submittedupdated Sep 2025Aug 2025—Sep 2025
Newfields Farm, Rownall Roadbattery storagebattery storage99.9approved, not builtupdated Jul 2025Jan 2025granted Jul 2025Jul 2025
Adj New House Farm, Luzlow Lanebattery storagebattery storage99refusedupdated Jan 2026Feb 2025refused Dec 2025Jan 2026
Tean Leys Farm, Tean Leysbattery storagebattery storage70application submittedupdated Jun 2025May 2025—Jun 2025
Armshead Farm, Armshead Roadbattery storagebattery storage50approved, not builtupdated Oct 2024Nov 2022refused Jun 2023Oct 2024
Upper Leigh Solar Farmsolar farmsolar farm49.9approved, not builtupdated Feb 2026Jan 2023granted Apr 2024Feb 2026
Solar Farm at New Buildings Solar Farmsolar farmsolar farm40application submittedupdated Nov 2025Sep 2025—Nov 2025
Draycott Cross Roadbattery storagebattery storage40approved, not builtupdated Jan 2024Jun 2023granted Jan 2024Jan 2024
Upper Newton Farm (Blythe House) Solar Farm & Battery Storagebattery storagebattery storage30approved, not builtupdated May 2026Mar 2022granted Feb 2023May 2026
Upper Newton Farm (Blythe House) Solar Farm & Battery Storagesolar farmsolar farm27.7approved, not builtupdated May 2026Mar 2022granted Feb 2023May 2026
Totmonslow Farm, Upper Tean Solar Farmsolar farmsolar farm19.8approved, not builtupdated Feb 2026Apr 2023granted Aug 2023Feb 2026
Blythe House Farm Extensionsolar farmsolar farm16.6approved, not builtupdated Feb 2026Nov 2023granted Jul 2024Feb 2026
Lower Newton Farmsolar farmsolar farm11.5operationalupdated Apr 2015Apr 2014granted Aug 2014Apr 2015
Land at Heywood Grangesolar farmsolar farm8.4operationalupdated Dec 2016Feb 2015granted Sep 2015Dec 2016
Moneystone Quarry Solar Farmsolar farmsolar farm5operationalupdated Nov 2016Apr 2015granted Jul 2015Nov 2016
The Fields Farmsolar farmsolar farm5refusedupdated Jan 2016Jul 2015refused Dec 2015Jan 2016
Cellarhead Substation, Rownall Roadbattery storagebattery storage2.6application submitted may be out of dateupdated Oct 2022Oct 2022—Oct 2022
Smaller schemes under 1 MW, mostly rooftop solar (6)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Cauldon Cement Works, Yelsway Lanerooftop solarrooftop solar0.5approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025
F Ball & Company Limited, Station Roadrooftop solarrooftop solar0.4approved, not builtupdated Jan 2024Oct 2023granted Dec 2023Jan 2024
Consall Hall Gardenssolar farmsolar farm0.3approved, not builtupdated Nov 2025Feb 2024granted Apr 2025Nov 2025
New Buildings Farm, Sharpley Heathrooftop solarrooftop solar0.2approved, not builtupdated Aug 2025Jun 2025granted Aug 2025Aug 2025
Goldhurst Distributions, Hollington Roadrooftop solarrooftop solar0.1approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026
Greenfields Farm, Thorney Edge Roadbattery storagebattery storage—application submittedupdated Oct 2024Oct 2024—Oct 2024

Postcode districts in Staffordshire Moorlands

DistrictProjects within 10 kmPendingApprovedOperational
ST8191160
ST9395302
ST10277154
ST11359203
ST1311460

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Staffordshire Moorlands by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.