Energy Projects Near You

Lower Newton Farm (11.5 MW solar farm)

Lower Newton Farm is an 11.5 MW solar farm project in Staffordshire Moorlands, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 16 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11.5 MWsolar farm
operationalstatus in REPD
16 April 2015record last updated
Staffordshire Moorlandscouncil area

Planning timeline

DateStage
25 April 2014Application submitted
26 August 2014Planning permission granted
1 November 2014Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
11.5 MW
Status (REPD)
operational
Record last updated
16 April 2015
Operator or applicant
Novus Solar Developments
Planning authority
Staffordshire Moorlands
Planning application reference
SMD/2014/0197
Site area
23.0 ha
Address (REPD)
Lower Newton Farm, Draycott Road, Tean, Stoke-On-Trent, Staffordshire
Council area (by location)
Staffordshire Moorlands
Time to decision
18 weeks
REPD reference
2032

Who decides

ApplicationsStaffordshire MoorlandsUK
Decided applications (solar, wind, battery)2510,236
Refused8 (32%)19%
Solar refused3 of 1512%
Battery storage refused5 of 1016%
Median time from submission to decision28.4 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Upper Newton Farm (Blythe House) Solar Farm & Battery Storagebattery storage30approved, not built<0.1
Upper Newton Farm (Blythe House) Solar Farm & Battery Storagesolar farm27.7approved, not built<0.1
Blythe House Farm Extensionsolar farm16.6approved, not built0.2
Totmonslow Farm, Upper Tean Solar Farmsolar farm19.8approved, not built1.1
Upper Leigh Solar Farmsolar farm49.9approved, not built2.2
Tean Leys Farm, Tean Leysbattery storage70application submitted2.4
Solar Farm at New Buildings Solar Farmsolar farm40application submitted2.9
Upper Leighbattery storage20application submitted3.0
The Fields Farmsolar farm5refused3.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9473, -2.0203).