Energy Projects Near You

Totmonslow Farm, Upper Tean Solar Farm (19.8 MW)

Totmonslow Farm, Upper Tean Solar Farm is a 19.8 MW solar farm project in Staffordshire Moorlands, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 August 2023, not yet built; the record was last updated on 20 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19.8 MWsolar farm
approved, not builtstatus in REPD
20 February 2026record last updated
Staffordshire Moorlandscouncil area

Planning timeline

DateStage
28 April 2023Application submitted
17 August 2023Planning permission granted
17 August 2026Permission expired

Project details

Technology
solar farm
Capacity
19.8 MW
Status (REPD)
approved, not built
Record last updated
20 February 2026
Operator or applicant
RE Projects Development Limited
Planning authority
Staffordshire Moorlands
Planning application reference
SMD/2023/0197
Site area
36.5 ha
Address (REPD)
Totmonslow Farm, Draycott Road, Totmonslow, Upper Tean
Council area (by location)
Staffordshire Moorlands
Time to decision
16 weeks
Contracts for Difference
AR7a
Name in REPD
Totmonslow Farm, Upper Tean - Solar Farm
REPD reference
13840

Who decides

ApplicationsStaffordshire MoorlandsUK
Decided applications (solar, wind, battery)2510,236
Refused8 (32%)19%
Solar refused3 of 1512%
Battery storage refused5 of 1016%
Median time from submission to decision28.4 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Blythe House Farm Extensionsolar farm16.6approved, not built1.0
Upper Newton Farm (Blythe House) Solar Farm & Battery Storagesolar farm27.7approved, not built1.1
Lower Newton Farmsolar farm11.5operational1.1
Upper Newton Farm (Blythe House) Solar Farm & Battery Storagebattery storage30approved, not built1.1
The Fields Farmsolar farm5refused2.2
Tean Leys Farm, Tean Leysbattery storage70application submitted2.3
Upper Leigh Solar Farmsolar farm49.9approved, not built2.3
Draycott Cross Roadbattery storage40approved, not built2.6
Upper Leighbattery storage20application submitted3.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9554, -2.0098).