Solar, wind and battery projects near Stoke-on-Trent (ST10)
27 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of ST10 (Staffordshire Moorlands): 7 are waiting for a planning decision, 15 approved but not yet running, 4 operational. The largest live scheme is Cellarhead Substation, Rownall Road (400 MW battery storage, application submitted on 13 February 2024, no decision recorded; REPD status may be out of date), 9.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of ST10
Projects of 1 MW and more (20)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Draycott Cross Roadbattery storage | battery storage | 40 | approved, not builtupdated Jan 2024 | Jun 2023 | granted Jan 2024 | Jan 2024 | Staffordshire Moorlands | 3.3 |
| Moneystone Quarry Solar Farmsolar farm | solar farm | 5 | operationalupdated Nov 2016 | Apr 2015 | granted Jul 2015 | Nov 2016 | Staffordshire Moorlands | 3.5 |
| The Fields Farmsolar farm | solar farm | 5 | refusedupdated Jan 2016 | Jul 2015 | refused Dec 2015 | Jan 2016 | Staffordshire Moorlands | 4.1 |
| Totmonslow Farm, Upper Tean Solar Farmsolar farm | solar farm | 19.8 | approved, not builtupdated Feb 2026 | Apr 2023 | granted Aug 2023 | Feb 2026 | Staffordshire Moorlands | 4.7 |
| Tean Leys Farm, Tean Leysbattery storage | battery storage | 70 | application submittedupdated Jun 2025 | May 2025 | — | Jun 2025 | Staffordshire Moorlands | 5.5 |
| Blythe House Farm Extensionsolar farm | solar farm | 16.6 | approved, not builtupdated Feb 2026 | Nov 2023 | granted Jul 2024 | Feb 2026 | Staffordshire Moorlands | 5.7 |
| Upper Leigh Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Feb 2026 | Jan 2023 | granted Apr 2024 | Feb 2026 | Staffordshire Moorlands | 5.8 |
| Upper Newton Farm (Blythe House) Solar Farm & Battery Storagebattery storage | battery storage | 30 | approved, not builtupdated May 2026 | Mar 2022 | granted Feb 2023 | May 2026 | Staffordshire Moorlands | 5.9 |
| Upper Newton Farm (Blythe House) Solar Farm & Battery Storagesolar farm | solar farm | 27.7 | approved, not builtupdated May 2026 | Mar 2022 | granted Feb 2023 | May 2026 | Staffordshire Moorlands | 5.9 |
| Lower Newton Farmsolar farm | solar farm | 11.5 | operationalupdated Apr 2015 | Apr 2014 | granted Aug 2014 | Apr 2015 | Staffordshire Moorlands | 5.9 |
| Land at Heywood Grangesolar farm | solar farm | 8.4 | operationalupdated Dec 2016 | Feb 2015 | granted Sep 2015 | Dec 2016 | Staffordshire Moorlands | 6.5 |
| Upper Leighbattery storage | battery storage | 20 | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 | East Staffordshire | 7.4 |
| Woodhouse Fields Farmsolar farm | solar farm | 5 | operationalupdated Jul 2018 | Aug 2015 | granted Nov 2015 | Jul 2018 | East Staffordshire | 7.7 |
| Leek Road, Werringtonbattery storage | battery storage | 300 | application submittedupdated Sep 2025 | Aug 2025 | — | Sep 2025 | Staffordshire Moorlands | 7.9 |
| Solar Farm at Leaford Solar Farmsolar farm | solar farm | 30 | application submitted may be out of dateupdated Jul 2024 | Jun 2024 | — | Jul 2024 | Stafford | 8.0 |
| Solar Farm at New Buildings Solar Farmsolar farm | solar farm | 40 | application submittedupdated Nov 2025 | Sep 2025 | — | Nov 2025 | Staffordshire Moorlands | 8.8 |
| Cellarhead Substation, Rownall Roadbattery storage | battery storage | 400 | application submitted may be out of dateupdated Apr 2024 | Feb 2024 | — | Apr 2024 | Staffordshire Moorlands | 9.5 |
| Cellarhead Substation, Rownall Roadbattery storage | battery storage | 2.6 | application submitted may be out of dateupdated Oct 2022 | Oct 2022 | — | Oct 2022 | Staffordshire Moorlands | 9.7 |
| Cellarhead Substation, Rownall Road Battery Energy Facilitybattery storage | battery storage | 400 | approved, not built may be out of dateupdated Jan 2023 | Aug 2022 | granted Dec 2022 | Jan 2023 | Staffordshire Moorlands | 9.7 |
| Newfields Farm, Rownall Roadbattery storage | battery storage | 99.9 | approved, not builtupdated Jul 2025 | Jan 2025 | granted Jul 2025 | Jul 2025 | Staffordshire Moorlands | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (7)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Goldhurst Distributions, Hollington Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Jun 2026 | Mar 2026 | granted May 2026 | Jun 2026 | Staffordshire Moorlands | 4.0 |
| Consall Hall Gardenssolar farm | solar farm | 0.3 | approved, not builtupdated Nov 2025 | Feb 2024 | granted Apr 2025 | Nov 2025 | Staffordshire Moorlands | 6.4 |
| Cauldon Cement Works, Yelsway Lanerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Dec 2024 | Jan 2025 | Staffordshire Moorlands | 8.6 |
| Unit 2, G-park, Whittle Roadrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Jun 2022 | Jun 2022 | granted Aug 2022 | Jun 2022 | Stoke-on-Trent | 8.7 |
| New Buildings Farm, Sharpley Heathrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2025 | Jun 2025 | granted Aug 2025 | Aug 2025 | Staffordshire Moorlands | 8.8 |
| VWS, Meirrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2025 | Feb 2025 | granted Mar 2025 | Mar 2025 | Stoke-on-Trent | 9.0 |
| Ormiston Meridian Academy, Sandon Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 | Stoke-on-Trent | 9.7 |
Distance from the average position of the ST10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 12 | 2 | 5 | 4 | 1 | 184 |
| Rooftop solar | 6 | 0 | 6 | 0 | 0 | 2.3 |
| Battery storage | 9 | 5 | 4 | 0 | 0 | 1,362 |
MW in pipeline: pending, approved and under-construction capacity.
How Staffordshire Moorlands decides solar, wind and battery applications
| Applications | Staffordshire Moorlands | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 25 | 10,236 |
| Refused | 8 (32%) | 19% |
| Solar refused | 3 of 15 | 12% |
| Battery storage refused | 5 of 10 | 16% |
| Median time from submission to decision | 28.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 1 | — |
All projects in Staffordshire Moorlands
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near ST10, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.