Solar, wind and battery projects near Uttoxeter (ST14)
21 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of ST14 (East Staffordshire): 4 are waiting for a planning decision, 5 approved but not yet running, 8 operational. The largest live scheme is Tean Leys Farm, Tean Leys (70 MW battery storage, application submitted on 22 May 2025, no decision recorded), 8.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of ST14
Projects of 1 MW and more (19)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Solar farm at land at The Willows, Uttoxetersolar farm | solar farm | 6.4 | operationalupdated Apr 2017 | Apr 2015 | granted Jul 2015 | Apr 2017 | East Staffordshire | 2.2 |
| Spring Farm (wind)wind farm | wind farm | 6 | application withdrawnupdated Dec 2008 | — | — | Dec 2008 | East Staffordshire | 3.2 |
| Twin Oaks Farmsolar farm | solar farm | 5 | abandonedupdated Sep 2018 | Jul 2015 | granted Oct 2015 | Sep 2018 | Derbyshire Dales | 3.9 |
| Marchington Solar Farmsolar farm | solar farm | 4.3 | operationalupdated Aug 2016 | Jul 2014 | granted Oct 2014 | Aug 2016 | East Staffordshire | 3.9 |
| Holtwood Farmsolar farm | solar farm | 5 | operationalupdated May 2016 | Aug 2015 | granted Oct 2015 | May 2016 | East Staffordshire | 4.6 |
| Woodhouse Fields Farmsolar farm | solar farm | 5 | operationalupdated Jul 2018 | Aug 2015 | granted Nov 2015 | Jul 2018 | East Staffordshire | 5.0 |
| Somersal Mill Farmsolar farm | solar farm | 2.6 | operationalupdated Mar 2016 | Feb 2015 | granted May 2015 | Mar 2016 | Derbyshire Dales | 5.2 |
| Bagot's Parkwind farm | wind farm | 18.4 | refusedupdated Apr 2011 | Oct 2007 | refused Apr 2011 | Apr 2011 | East Staffordshire | 6.6 |
| Marchington Solar Parksolar farm | solar farm | 4.2 | abandonedupdated Dec 2015 | Jan 2011 | granted Aug 2013 | Dec 2015 | East Staffordshire | 6.7 |
| Land of Green Lanesolar farm | solar farm | 5.8 | operationalupdated Apr 2017 | Jul 2015 | granted Sep 2015 | Apr 2017 | East Staffordshire | 6.8 |
| Morton House (Marchington)solar farm | solar farm | 6.2 | operationalupdated Sep 2016 | Apr 2015 | granted Jul 2015 | Sep 2016 | East Staffordshire | 7.2 |
| Tean Leys Farm, Tean Leysbattery storage | battery storage | 70 | application submittedupdated Jun 2025 | May 2025 | — | Jun 2025 | Staffordshire Moorlands | 8.8 |
| Upper Leighbattery storage | battery storage | 20 | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 | East Staffordshire | 8.9 |
| Upper Leigh Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Feb 2026 | Jan 2023 | granted Apr 2024 | Feb 2026 | Staffordshire Moorlands | 8.9 |
| Aston House Solar Farmsolar farm | solar farm | 20 | operationalupdated May 2015 | Jul 2014 | granted Nov 2014 | May 2015 | Derbyshire Dales | 8.9 |
| Yew Tree Farm, Drointon Lanesolar farm | solar farm | 49 | application submittedupdated Jun 2025 | May 2025 | — | Jun 2025 | Stafford | 9.2 |
| Yew Tree Farm, Drointon Lanebattery storage | battery storage | 30 | application submittedupdated Jun 2025 | May 2025 | — | Jun 2025 | Stafford | 9.2 |
| Lower Farm, Drointon Lane Solar farm & Battery Energy Storagesolar farm | solar farm | 49.9 | approved, not builtupdated Feb 2026 | Mar 2023 | granted Jan 2025 | Feb 2026 | Stafford | 9.5 |
| Lower Farm, Drointon Lane Solar farm & Battery Energy Storagebattery storage | battery storage | 30 | approved, not builtupdated Feb 2026 | Mar 2023 | granted Jan 2025 | Feb 2026 | Stafford | 9.5 |
Smaller schemes under 1 MW, mostly rooftop solar (2)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Uttoxeter Leisure Centre, Oldfields Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2025 | Jun 2025 | granted Jul 2025 | Aug 2025 | East Staffordshire | 0.9 |
| Goldhurst Distributions, Hollington Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Jun 2026 | Mar 2026 | granted May 2026 | Jun 2026 | Staffordshire Moorlands | 7.8 |
Distance from the average position of the ST14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 13 | 1 | 2 | 8 | 0 | 149 |
| Rooftop solar | 2 | 0 | 2 | 0 | 0 | 0.4 |
| Wind farm | 2 | 0 | 0 | 0 | 1 | 0 |
| Battery storage | 4 | 3 | 1 | 0 | 0 | 150 |
MW in pipeline: pending, approved and under-construction capacity.
How East Staffordshire decides solar, wind and battery applications
| Applications | East Staffordshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 21 | 10,236 |
| Refused | 1 (5%) | 19% |
| Solar refused | 0 of 19 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 0 of 1 | 16% |
| Median time from submission to decision | 11.7 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
All projects in East Staffordshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.