Twin Oaks Farm (5 MW solar farm)

Twin Oaks Farm is a 5 MW solar farm project in Derbyshire Dales, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 27 September 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
abandonedstatus in REPD
27 September 2018record last updated
Derbyshire Dalescouncil area

Planning timeline

DateStage
23 July 2015Application submitted
14 October 2015Planning permission granted
14 October 2018Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
abandoned
Record last updated
27 September 2018
Operator or applicant
Global Renewable Construction
Planning authority
Derbyshire Dales
Planning application reference
15/00527/FUL
Site area
9.8 ha
Address (REPD)
Twin Oaks Yelt Lane, Doveridge
Council area (by location)
Derbyshire Dales
Time to decision
12 weeks
REPD reference
5935

Who decides

ApplicationsDerbyshire DalesUK
Decided applications (solar, wind, battery)2210,236
Refused5 (23%)19%
Solar refused2 of 1712%
Onshore wind refused3 of 545%
Median time from submission to decision12.9 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Holtwood Farmsolar farm5operational1.2
Solar farm at land at The Willows, Uttoxetersolar farm6.4operational1.8
Land of Green Lanesolar farm5.8operational3.3
Morton House (Marchington)solar farm6.2operational3.7
Aston House Solar Farmsolar farm20operational5.1
Spring Farm (wind)wind farm6application withdrawn6.8
Woodhouse Fields Farmsolar farm5operational6.8
Bagot's Parkwind farm18.4refused7.2
Hawthorn Farmsolar farm10under construction7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.898, -1.8139).