Energy Projects Near You

Spring Farm (wind) (6 MW)

Spring Farm (wind) is a 6 MW wind farm project in East Staffordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 4 December 2008; the record was last updated on 4 December 2008.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWwind farm
application withdrawnstatus in REPD
4 December 2008record last updated
East Staffordshirecouncil area

Planning timeline

DateStage
4 December 2008Application withdrawn

Project details

Technology
wind farm
Capacity
6 MW
Status (REPD)
application withdrawn
Record last updated
4 December 2008
Operator or applicant
Ecotricity
Planning authority
East Staffordshire
Planning application reference
not recorded
Turbines
3
Address (REPD)
Spring Farm Bramshall
Council area (by location)
East Staffordshire
REPD reference
3209

Who decides

ApplicationsEast StaffordshireUK
Decided applications (solar, wind, battery)2110,236
Refused1 (5%)19%
Solar refused0 of 1912%
Onshore wind refused1 of 145%
Battery storage refused0 of 116%
Median time from submission to decision11.7 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Solar farm at land at The Willows, Uttoxetersolar farm6.4operational5.0
Bagot's Parkwind farm18.4refused6.2
Upper Leighbattery storage20application submitted6.4
Yew Tree Farm, Drointon Lanesolar farm49application submitted6.7
Woodhouse Fields Farmsolar farm5operational6.7
Twin Oaks Farmsolar farm5abandoned6.8
Tean Leys Farm, Tean Leysbattery storage70application submitted7.0
Lower Farm, Drointon Lane Solar farm & Battery Energy Storagesolar farm49.9approved, not built7.0
Upper Leigh Solar Farmsolar farm49.9approved, not built7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.8953, -1.915).