Energy Projects Near You

Solar, wind and battery projects near Ashbourne (DE6)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DE6 (Derbyshire Dales): 1 is waiting for a planning decision, 2 approved but not yet running, 4 operational. The largest live scheme is Solar Panels at Brailsford Solar Park (55 MW solar farm, application submitted on 6 May 2026, no decision recorded), 6.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
1awaiting a decision
2approved, not running
4operational

Projects within 10 km of DE6

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Lady Hole Farmsolar farmsolar farm3operationalupdated May 2016Apr 2015granted Jul 2015May 2016Derbyshire Dales2.6
Land at Dayfields Farmsolar farmsolar farm4.7operationalupdated Apr 2017Mar 2015granted Mar 2016Apr 2017Derbyshire Dales5.6
Solar Panels at Brailsford Solar Parksolar farmsolar farm55application submittedupdated Jul 2026May 2026—Jul 2026Derbyshire Dales6.8
Brailsford Farmsolar farmsolar farm1.2abandonedupdated Oct 2018Sep 2015granted Dec 2015Oct 2018Derbyshire Dales7.1
Smith Hall Farm Solar Parksolar farmsolar farm5operationalupdated Feb 2017Jun 2014granted Sep 2014Feb 2017Derbyshire Dales8.0
Somersal Mill Farmsolar farmsolar farm2.6operationalupdated Mar 2016Feb 2015granted May 2015Mar 2016Derbyshire Dales9.8
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Derbyshire Aggregates Dalton Central Hubrooftop solarrooftop solar0.2approved, not builtupdated Apr 2026Jan 2026granted Mar 2026Apr 2026Derbyshire Dales1.8
Aggregate Industries, Smith Hall Lanerooftop solarrooftop solar0.5approved, not builtupdated Jun 2023Mar 2023granted May 2023Jun 2023Derbyshire Dales7.4

Distance from the average position of the DE6 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm6104055
Rooftop solar202000.8

MW in pipeline: pending, approved and under-construction capacity.

How Derbyshire Dales decides solar, wind and battery applications

ApplicationsDerbyshire DalesUK
Decided applications (solar, wind, battery)2210,236
Refused5 (23%)19%
Solar refused2 of 1712%
Onshore wind refused3 of 545%
Median time from submission to decision12.9 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

All projects in Derbyshire Dales

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.