Solar, wind and battery projects near Leek (ST13)
11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of ST13 (Staffordshire Moorlands): 4 are waiting for a planning decision, 6 approved but not yet running. The largest live scheme is Cellarhead Substation, Rownall Road Battery Energy Facility (400 MW battery storage, approved on 22 December 2022, not yet built; REPD status may be out of date), 7.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of ST13
Projects of 1 MW and more (8)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Newfields Farm, Rownall Roadbattery storage | battery storage | 99.9 | approved, not builtupdated Jul 2025 | Jan 2025 | granted Jul 2025 | Jul 2025 | Staffordshire Moorlands | 7.0 |
| Cellarhead Substation, Rownall Road Battery Energy Facilitybattery storage | battery storage | 400 | approved, not built may be out of dateupdated Jan 2023 | Aug 2022 | granted Dec 2022 | Jan 2023 | Staffordshire Moorlands | 7.5 |
| Cellarhead Substation, Rownall Roadbattery storage | battery storage | 2.6 | application submitted may be out of dateupdated Oct 2022 | Oct 2022 | — | Oct 2022 | Staffordshire Moorlands | 7.8 |
| Cellarhead Substation, Rownall Roadbattery storage | battery storage | 400 | application submitted may be out of dateupdated Apr 2024 | Feb 2024 | — | Apr 2024 | Staffordshire Moorlands | 8.2 |
| Adj New House Farm, Luzlow Lanebattery storage | battery storage | 99 | refusedupdated Jan 2026 | Feb 2025 | refused Dec 2025 | Jan 2026 | Staffordshire Moorlands | 8.5 |
| Armshead Farm, Armshead Roadbattery storage | battery storage | 50 | approved, not builtupdated Oct 2024 | Nov 2022 | refused Jun 2023 | Oct 2024 | Staffordshire Moorlands | 9.2 |
| Leek Road, Werringtonbattery storage | battery storage | 300 | application submittedupdated Sep 2025 | Aug 2025 | — | Sep 2025 | Staffordshire Moorlands | 9.2 |
| Brown Edgebattery storage | battery storage | 49.5 | approved, not builtupdated May 2025 | Mar 2022 | granted May 2025 | May 2025 | Stoke-on-Trent | 9.8 |
Smaller schemes under 1 MW, mostly rooftop solar (3)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| F Ball & Company Limited, Station Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jan 2024 | Oct 2023 | granted Dec 2023 | Jan 2024 | Staffordshire Moorlands | 3.6 |
| Consall Hall Gardenssolar farm | solar farm | 0.3 | approved, not builtupdated Nov 2025 | Feb 2024 | granted Apr 2025 | Nov 2025 | Staffordshire Moorlands | 7.2 |
| Greenfields Farm, Thorney Edge Roadbattery storage | battery storage | — | application submittedupdated Oct 2024 | Oct 2024 | — | Oct 2024 | Staffordshire Moorlands | 8.1 |
Distance from the average position of the ST13 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 1 | 0 | 1 | 0 | 0 | 0.3 |
| Rooftop solar | 1 | 0 | 1 | 0 | 0 | 0.4 |
| Battery storage | 9 | 4 | 4 | 0 | 1 | 1,302 |
MW in pipeline: pending, approved and under-construction capacity.
How Staffordshire Moorlands decides solar, wind and battery applications
| Applications | Staffordshire Moorlands | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 25 | 10,236 |
| Refused | 8 (32%) | 19% |
| Solar refused | 3 of 15 | 12% |
| Battery storage refused | 5 of 10 | 16% |
| Median time from submission to decision | 28.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 1 | — |
All projects in Staffordshire Moorlands
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near ST13, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.