Energy Projects Near You

Blythe House Farm Extension (16.6 MW solar farm)

Blythe House Farm Extension is a 16.6 MW solar farm project in Staffordshire Moorlands, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 22 July 2024, not yet built; the record was last updated on 16 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16.6 MWsolar farm
approved, not builtstatus in REPD
16 February 2026record last updated
Staffordshire Moorlandscouncil area

Planning timeline

DateStage
29 November 2023Application submitted
22 July 2024Planning permission granted

Project details

Technology
solar farm
Capacity
16.6 MW
Status (REPD)
approved, not built
Record last updated
16 February 2026
Operator or applicant
Innova Renewables
Planning authority
Staffordshire Moorlands
Planning application reference
SMD/2023/0594
Site area
24.1 ha
Address (REPD)
Blythe House Farm, S/O The A50, Stoke on Trent
Council area (by location)
Staffordshire Moorlands
Time to decision
34 weeks
Name in REPD
Blythe House Farm Extension - Solar Array
REPD reference
15586

Who decides

ApplicationsStaffordshire MoorlandsUK
Decided applications (solar, wind, battery)2510,236
Refused8 (32%)19%
Solar refused3 of 1512%
Battery storage refused5 of 1016%
Median time from submission to decision28.4 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Upper Newton Farm (Blythe House) Solar Farm & Battery Storagebattery storage30approved, not built0.2
Lower Newton Farmsolar farm11.5operational0.2
Upper Newton Farm (Blythe House) Solar Farm & Battery Storagesolar farm27.7approved, not built0.2
Totmonslow Farm, Upper Tean Solar Farmsolar farm19.8approved, not built1.0
Upper Leigh Solar Farmsolar farm49.9approved, not built2.1
Tean Leys Farm, Tean Leysbattery storage70application submitted2.2
Upper Leighbattery storage20application submitted2.9
The Fields Farmsolar farm5refused2.9
Solar Farm at New Buildings Solar Farmsolar farm40application submitted3.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.9479, -2.017).