Noriker Power Staunch (20 MW battery storage)

Noriker Power Staunch is a 20 MW battery storage project in Newcastle-under-Lyme, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2017; the record was last updated on 9 May 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
operationalstatus in REPD
9 May 2019record last updated
Newcastle-under-Lymecouncil area

Planning timeline

DateStage
24 March 2016Application submitted
19 May 2016Planning permission granted
15 December 2016Construction started
15 March 2017Operational

Project details

Technology
battery storage (co-located with fossil fuel plant)
Capacity
20 MW
Status (REPD)
operational
Record last updated
9 May 2019
Operator or applicant
Hazel Capital/ Noriker Power
Planning authority
Newcastle-under-Lyme
Planning application reference
16/00242/FUL
Address (REPD)
Holditch House, Holditch Road, Chesterton
Council area (by location)
Newcastle-under-Lyme
Time to decision
8 weeks
REPD reference
6918

Who decides

ApplicationsNewcastle-under-LymeUK
Decided applications (solar, wind, battery)1710,236
Refused0 (0%)19%
Solar refused0 of 1012%
Onshore wind refused0 of 245%
Battery storage refused0 of 516%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Rubber and Allied Productsbattery storage40approved, not built0.4
Brown Edgebattery storage49.5approved, not built7.3
Armshead Farm, Armshead Roadbattery storage50approved, not built9.8
Adj New House Farm, Luzlow Lanebattery storage99refused9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.0329, -2.2433).