Landown Farm, Bakeacre Lane (40 MW battery storage)

Landown Farm, Bakeacre Lane is a 40 MW battery storage project in South Derbyshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 May 2025, not yet built; the record was last updated on 17 June 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWbattery storage
approved, not builtstatus in REPD
17 June 2025record last updated
South Derbyshirecouncil area

Planning timeline

DateStage
19 December 2024Application submitted
30 May 2025Planning permission granted
30 May 2030Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
17 June 2025
Operator or applicant
Integrum Renewable Energy Limited
Planning authority
South Derbyshire
Planning application reference
DMPA/2024/1639
Address (REPD)
Landown Farm, Bakeacre Lane, Findern, Derby
Council area (by location)
South Derbyshire
Time to decision
23 weeks
Name in REPD
Landown Farm, Bakeacre Lane - Battery Energy Storage System
REPD reference
16308

Who decides

ApplicationsSouth DerbyshireUK
Decided applications (solar, wind, battery)2610,236
Refused5 (19%)19%
Solar refused4 of 1412%
Battery storage refused1 of 1216%
Median time from submission to decision28.6 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Solar Farm at Toyota Manufacturing Ukrooftop solar16application submitted2.0
Arleston Solar & Battery Energy Storage Systemsolar farm43application submitted3.0
Stenson Lanebattery storage400approved, not built3.0
Derby Road, Eggintonbattery storage100approved, not built5.2
Newton Solney Solar Farmsolar farm21.1refused7.0
Rollston on Dove, Marston Lanesolar farm5abandoned7.5
Claymills Sewage Treatment Works, Meadow Lanesolar farm25application submitted8.3
Hoon Hay Manor, Hatton Solar Farmsolar farm5.1approved, not built8.9
Derby Sewage Treatment Workswind farm5operational9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.8773, -1.5384).