Energy Projects Near You

Solar, wind and battery projects near Porthcawl (CF36)

14 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CF36 (Bridgend): 3 are waiting for a planning decision, 3 approved but not yet running, 7 operational. The largest live scheme is Kenfig Industrial Estate, Margam (1.5 MW wind turbine, approved on 29 September 2022, not yet built), 6.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14projects within 10 km
3awaiting a decision
3approved, not running
7operational

Projects within 10 km of CF36

Projects of 1 MW and more (9)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Seaview Farmsolar farmsolar farm1.7operationalupdated Jul 2016Mar 2014granted Jun 2014Jul 2016Bridgend1.2
Newton Downwind farmwind farm5operationalupdated Oct 2016May 2012granted May 2013Oct 2016Bridgend2.8
Parc Stormy, Stormy Downwind turbinewind turbine2.5operationalupdated Jul 2020Jan 2016granted Aug 2016Jul 2020Bridgend3.2
Stormy Down Solar Farmsolar farmsolar farm3.8operationalupdated Dec 2017May 2015granted Aug 2015Dec 2017Bridgend3.6
Caergarw Farmsolar farmsolar farm3.8operationalupdated Jul 2017Nov 2015granted May 2016Jul 2017Neath Port Talbot6.1
Kenfig Industrial Estate, Margamwind turbinewind turbine1.5approved, not builtupdated Jun 2022May 2022granted Sep 2022Jun 2022Neath Port Talbot6.3
Court Colman solar parksolar farmsolar farm15operationalupdated Jan 2016May 2014granted Dec 2014Jan 2016Bridgend7.0
Court Colmansolar farmsolar farm1permission expiredupdated Dec 2019May 2017granted Aug 2017Dec 2019Bridgend8.0
Longlands Lanewind turbinewind turbine1.5operationalupdated May 2015Oct 2012granted Nov 2013May 2015Neath Port Talbot9.3
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Margamrooftop solarrooftop solar0.4approved, not builtupdated Jun 2022Jun 2022granted Jul 2022Jun 2022Neath Port Talbot6.2
Cwm Risca Farm, Tonduwind farmwind farm0.5application submittedupdated Dec 2025Oct 2025—Dec 2025Bridgend9.1
Great Western Avenue, Coity Roadbattery storagebattery storage—approved, not builtupdated Apr 2022Mar 2022granted Jun 2022Apr 2022Bridgend9.1
Princess Of Wales Hospital, Coity Roadrooftop solarrooftop solar0.9application submittedupdated Mar 2026Mar 2026—Mar 2026Bridgend9.6
Princess Of Wales Hospital, Coity Roadrooftop solarrooftop solar0.7application submittedupdated Mar 2026Mar 2026—Mar 2026Bridgend9.6

Distance from the average position of the CF36 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm500400
Rooftop solar321002
Wind farm210100.5
Wind turbine301201.5
Battery storage101000

MW in pipeline: pending, approved and under-construction capacity.

How Bridgend decides solar, wind and battery applications

ApplicationsBridgendUK
Decided applications (solar, wind, battery)1910,236
Refused7 (37%)19%
Solar refused1 of 812%
Onshore wind refused6 of 1045%
Battery storage refused0 of 116%
Median time from submission to decision23.7 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

All projects in Bridgend

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.