Court Colman solar park (15 MW)

Court Colman solar park is a 15 MW solar farm project in Bridgend, Wales. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 November 2015; the record was last updated on 11 January 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWsolar farm
operationalstatus in REPD
11 January 2016record last updated
Bridgendcouncil area

Planning timeline

DateStage
13 May 2014Application submitted
24 December 2014Planning permission granted
1 July 2015Construction started
15 November 2015Operational

Project details

Technology
solar farm
Capacity
15 MW
Status (REPD)
operational
Record last updated
11 January 2016
Operator or applicant
Suncredit UK/ Vogt Solar
Planning authority
Bridgend
Planning application reference
P/14/337/FUL
Address (REPD)
LAND AT COURT COLMAN PENYFAI BRIDGEND
Council area (by location)
Bridgend
Time to decision
32 weeks
REPD reference
1982

Who decides

ApplicationsBridgendUK
Decided applications (solar, wind, battery)1910,236
Refused7 (37%)19%
Solar refused1 of 812%
Onshore wind refused6 of 1045%
Battery storage refused0 of 116%
Median time from submission to decision23.7 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Newton Downwind farm5operational4.2
Ty’n y Waun Solar Farm (Bridgend Energy Hub)solar farm40approved, not built7.2
Pant y wal extensionwind farm20operational9.8
Y Bryn Wind Farmwind farm130refused9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5227, -3.6187).