Energy Projects Near You

Solar, wind and battery projects near Sidcup (DA14)

49 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of DA14 (Bexley): 4 are waiting for a planning decision, 35 approved but not yet running, 4 operational. The largest live scheme is Manor Farm, Dartford Road (212 MW battery storage, application submitted on 5 June 2025, no decision recorded), 3.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49projects within 10 km
4awaiting a decision
35approved, not running
4operational

Projects within 10 km of DA14

Projects of 1 MW and more (12)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
North Cray Roadbattery storagebattery storage200refusedupdated Jan 2026Apr 2025refused Oct 2025Jan 2026Bexley1.6
Manor Farm, Dartford Roadbattery storagebattery storage212application submittedupdated Jul 2025Jun 2025—Jul 2025Bexley3.4
Queen Elizabeth Hospital, Stadium Roadrooftop solarrooftop solar1.6refusedupdated Dec 2025Oct 2025refused Nov 2025Dec 2025Greenwich7.3
Darenth Roadbattery storagebattery storage99.9approved, not builtupdated Oct 2025May 2025granted Oct 2025Oct 2025Dartford8.4
Crossness Sewage Works Turbinewind turbinewind turbine2.5operationalupdated Jan 2015Nov 2010granted Dec 2010Jan 2015Bexley8.8
Horton Wood Solar parksolar farmsolar farm49.9approved, not built may be out of dateupdated Aug 2025Oct 2022granted Feb 2023Aug 2025Sevenoaks9.2
Riverside Energy Parkbattery storagebattery storage20approved, not built may be out of dateupdated Apr 2022Nov 2018granted Apr 2020Apr 2022Bexley9.3
Riverside Energy Park (REP)rooftop solarrooftop solar1approved, not built may be out of dateupdated Sep 2020Nov 2018granted Apr 2020Sep 2020Bexley9.3
Riverside Resource Recovery Facility Battery Storagebattery storagebattery storage2.5under constructionupdated Jan 2021Dec 2020—Jan 2021Bexley9.4
Crossness Sewage Works PVrooftop solarrooftop solar1.5operationalupdated Jan 2012——Jan 2012Bexley9.4
Thameside DCrooftop solarrooftop solar1operationalupdated Feb 2016——Feb 2016Greenwich9.5
Neatscourtbattery storagebattery storage1abandonedupdated Jun 2020Jun 2017—Jun 2020Dartford9.7
Smaller schemes under 1 MW, mostly rooftop solar (37)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
David Lloyd Leisure, Baugh Roadrooftop solarrooftop solar—approved, not builtupdated Jan 2026Jul 2025granted Sep 2025Jan 2026Bexley0.7
Maidstone Roadrooftop solarrooftop solar0.3approved, not builtupdated Dec 2023Oct 2023granted Dec 2023Dec 2023Bexley0.9
Tesco Stores Limited, Edgington Wayrooftop solarrooftop solar0.2approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025Bromley1.6
Avery Hill Campus, Avery Hill Roadrooftop solarrooftop solar0.5approved, not builtupdated May 2026Feb 2026granted Mar 2026May 2026Greenwich3.2
Bexleyheath Superbowl, Albion Roadrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Bexley4.1
The Mallrooftop solarrooftop solar—approved, not builtupdated Mar 2026Nov 2025granted Jan 2026Mar 2026Bexley4.2
White Oak Leisure Centre, Hilda May Avenuerooftop solarrooftop solar0.4approved, not builtupdated Jan 2025Nov 2024granted Dec 2024Jan 2025Sevenoaks4.9
Dartford Grammar School For Boys, West Hillrooftop solarrooftop solar0.2approved, not builtupdated Sep 2024Jul 2024granted Sep 2024Sep 2024Dartford6.9
Pavilion Leisure Centre, Kentish Wayrooftop solarrooftop solar0.2approved, not builtupdated Apr 2023Mar 2023granted Apr 2023Apr 2023Bromley7.0
J Sainsbury, Walters Yardrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Apr 2026granted Jun 2026Jun 2026Bromley7.1
David Lloyd Leisure Limited, Corner Of Weigall Roadrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Greenwich7.1
Downham Health & Leisure Centre, Moorside Roadrooftop solarrooftop solar0.2approved, not builtupdated Apr 2025Jan 2025granted Mar 2025Apr 2025Lewisham7.1
Brookhill Estate Regenerationrooftop solarrooftop solar0.1approved, not built may be out of dateupdated May 2022Apr 2022granted Mar 2023May 2022Greenwich7.3
Fairfield Pool, Lowfield Streetrooftop solarrooftop solar0.4approved, not builtupdated Oct 2023Jul 2023granted Oct 2023Oct 2023Dartford7.4
Fairfield Centre, Lowfield Streetrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Dartford7.4
The I O Centre, Skeffington Streetrooftop solarrooftop solar0.2refusedupdated Feb 2026Nov 2025refused Jan 2026Feb 2026Greenwich7.8
James Watt Wayrooftop solarrooftop solar0.6approved, not builtupdated Nov 2021Nov 2021granted Jan 2022Nov 2021Bexley7.9
Northern Gateway Distribution Centre, Central Road Northrooftop solarrooftop solar0.8approved, not builtupdated Jan 2024Nov 2023granted Jan 2024Jan 2024Dartford8.1
Northern Gateway Distribution Centre,Central Road Northrooftop solarrooftop solar0.6application submittedJun 2026——Dartford8.1
David Lloyd Sports Centre, Darenth Road Solar Photo Voltaic Systemrooftop solarrooftop solar0.3approved, not builtupdated Jan 2024Nov 2023granted Jan 2024Jan 2024Dartford8.1
Thames Innovation Centre, Veridion Wayrooftop solarrooftop solar0.2approved, not builtupdated Sep 2025May 2025granted Jul 2025Sep 2025Bexley8.2
The Valley, Floyd Roadrooftop solarrooftop solar0.7approved, not builtupdated Aug 2025Jun 2025granted Jul 2025Aug 2025Greenwich8.6
Siemens Roadrooftop solarrooftop solar0.7refusedupdated Jun 2023Apr 2023refused Jun 2023Jun 2023Greenwich9.0
Siemens Road, Westminster Industrial Estaterooftop solarrooftop solar0.7approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Greenwich9.0
Siemens Road, Westminster Industrial Estaterooftop solarrooftop solar0.7approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Greenwich9.0
Swan Road, Westminster Industrial Estaterooftop solarrooftop solar0.7refusedupdated Jun 2023Apr 2023refused Jun 2023Jun 2023Greenwich9.0
One Hundred House, Brunel Wayrooftop solarrooftop solar0.8approved, not builtupdated Aug 2023Jul 2023granted Aug 2023Aug 2023Dartford9.0
Stone Lake Retail Park, Woolwich Roadrooftop solarrooftop solar0.1approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026Greenwich9.0
Twin Tumps Wayrooftop solarrooftop solar0.6operationalupdated Mar 2022Feb 2022granted Dec 2022Mar 2022Greenwich9.0
Littlebrook Hospital, Bow Arrow Lanerooftop solarrooftop solar—approved, not builtupdated Jul 2026Apr 2026granted Jun 2026Jul 2026Dartford9.3
Sedgehill Academy, Sedgehill Roadrooftop solarrooftop solar0.4approved, not builtupdated Jan 2026Sep 2025granted Nov 2025Jan 2026Lewisham9.3
Princes Roadrooftop solarrooftop solar0.1approved, not builtupdated Jan 2023Nov 2022granted Jan 2023Jan 2023Dartford9.4
Atlantis Avenue, Beckton Solar PV Systemsrooftop solarrooftop solar0.4approved, not builtupdated Jun 2023Apr 2023granted Jun 2023Jun 2023Newham9.5
University Of East London Dockland Campus, University Way - Soalr Panelsrooftop solarrooftop solar—approved, not builtupdated Jan 2024Oct 2023granted Dec 2023Jan 2024Newham9.7
London Design and Engineering UTC, University Waywind farmwind farm0.2application submittedMay 2026——Newham9.8
Millennium Retail Park - Flats & Retail Spacerooftop solarrooftop solar0.3application submitted may be out of dateupdated Sep 2024May 2024—Sep 2024Greenwich9.8
Knowledge Dock, University Wayrooftop solarrooftop solar0.1approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Newham9.8

Distance from the average position of the DA14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm1010049.9
Rooftop solar402313411.2
Wind farm110000.2
Wind turbine100100
Battery storage61301334

MW in pipeline: pending, approved and under-construction capacity.

How Bexley decides solar, wind and battery applications

Bexley has 8 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

All projects in Bexley

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near DA14, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.