Solar, wind and battery projects near Sandhurst (GU47)
28 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of GU47 (Bracknell Forest): 3 are waiting for a planning decision, 18 approved but not yet running, 3 operational. The largest live scheme is Barkham Farms Solar Farm (33 MW solar farm, approved on 21 January 2022, not yet built; REPD status may be out of date), 6.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of GU47
Projects of 1 MW and more (9)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Stanhope Roadrooftop solar | rooftop solar | 1.2 | refusedupdated May 2024 | Jan 2024 | refused Mar 2024 | May 2024 | Surrey Heath | 2.5 |
| Stanhope Roadrooftop solar | rooftop solar | 1.2 | refusedupdated Jul 2024 | May 2024 | refused Jul 2024 | Jul 2024 | Surrey Heath | 2.5 |
| Data Centre, Dennison House, Stanhope Roadrooftop solar | rooftop solar | 1.1 | approved, not builtupdated Jan 2025 | Nov 2024 | granted Jan 2025 | Jan 2025 | Surrey Heath | 2.7 |
| Barkham Farms Solar Farmsolar farm | solar farm | 33 | approved, not built may be out of dateupdated Feb 2021 | Mar 2021 | granted Jan 2022 | Feb 2021 | Wokingham | 6.9 |
| Farnborough Airportrooftop solar | rooftop solar | 1.7 | operationalupdated Nov 2024 | Aug 2023 | granted Oct 2023 | Nov 2024 | Rushmoor | 7.4 |
| Farnborough International Exhibition Centre, Etps Roadrooftop solar | rooftop solar | 1.1 | under constructionupdated Feb 2024 | Dec 2023 | granted Feb 2024 | Feb 2024 | Rushmoor | 8.3 |
| Taplins Farm solar parksolar farm | solar farm | 5.9 | operationalupdated Jul 2016 | May 2014 | granted Oct 2014 | Jul 2016 | Hart | 9.3 |
| Aborfield Solar Parksolar farm | solar farm | 14 | under constructionupdated Apr 2021 | Mar 2020 | granted Mar 2021 | Apr 2021 | Wokingham | 9.9 |
| Hungerford Farmsolar farm | solar farm | 5 | operationalupdated Oct 2016 | Jul 2015 | granted Oct 2015 | Oct 2016 | Hart | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (19)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Edgbarrow School, Grant Roadrooftop solar | rooftop solar | 0.2 | approved, not built | Apr 2026 | granted Jun 2026 | — | Bracknell Forest | 1.5 |
| Tesco Stores, Marshall Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Bracknell Forest | 1.8 |
| The Paddock Centre, Joshua Jebb Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2025 | Dec 2024 | granted Jan 2025 | Feb 2025 | Bracknell Forest | 2.2 |
| Broadmoor Hospital, Lower Broadmoor Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Apr 2026 | Mar 2025 | granted Feb 2026 | Apr 2026 | Bracknell Forest | 2.6 |
| Gbc Uk, Glebeland Roadrooftop solar | rooftop solar | 0.2 | application submitted | Mar 2026 | — | — | Surrey Heath | 2.7 |
| Contra House, Oak Closerooftop solar | rooftop solar | 0.3 | application submitted | Jun 2026 | — | — | Surrey Heath | 3.0 |
| West Side Of France Hill Drivebattery storage | battery storage | 0.2 | approved, not builtupdated Jul 2025 | Mar 2025 | granted Jul 2025 | Jul 2025 | Surrey Heath | 3.1 |
| South Camberley Adult Learning Centre - Micro Energy Storage Projectbattery storage | battery storage | 0.2 | application withdrawnupdated Nov 2024 | Aug 2024 | — | Nov 2024 | Surrey Heath | 3.3 |
| Chancerygate Wayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2024 | Mar 2024 | granted May 2024 | May 2024 | Rushmoor | 4.9 |
| Chancerygate Wayrooftop solar | rooftop solar | 0.3 | abandonedupdated Feb 2021 | Jan 2020 | — | Feb 2021 | Rushmoor | 5.0 |
| David Lloyd Royal Berkshirerooftop solar | rooftop solar | — | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Bracknell Forest | 5.2 |
| St Michaels Abbey, Farnborough Roadsolar farm | solar farm | 0.2 | approved, not builtupdated Jun 2026 | Jan 2026 | granted Apr 2026 | Jun 2026 | Rushmoor | 6.6 |
| Invincible Roadrooftop solar | rooftop solar | 0.1 | approved, not built may be out of dateupdated Jun 2023 | May 2023 | granted Jun 2023 | Jun 2023 | Rushmoor | 7.1 |
| John Nike Way, Binfieldsolar farm | solar farm | 0.8 | application submittedupdated Mar 2026 | Feb 2026 | — | Mar 2026 | Bracknell Forest | 7.3 |
| Templer Avenue Solar Photovoltaic Panelsolar farm | solar farm | 0.2 | approved, not builtupdated Dec 2022 | Nov 2022 | granted Dec 2022 | Dec 2022 | Rushmoor | 7.4 |
| Rectory Roadrooftop solar | rooftop solar | — | approved, not built may be out of dateupdated Apr 2021 | Jan 2021 | granted Apr 2021 | Apr 2021 | Wokingham | 7.7 |
| Heatherwood Hospital, Brook Avenuerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Windsor and Maidenhead | 9.8 |
| Heatherwood Hospital, Brook Avenuebattery storage | battery storage | — | approved, not builtupdated Jan 2026 | Dec 2025 | granted Jan 2026 | Jan 2026 | Windsor and Maidenhead | 9.8 |
| Henry Street Garden Centre, Swallowfield Road,rooftop solar | rooftop solar | 0.4 | approved, not builtupdated Dec 2023 | Nov 2023 | granted Nov 2023 | Dec 2023 | Wokingham | 9.9 |
Distance from the average position of the GU47 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 7 | 1 | 4 | 2 | 0 | 48.2 |
| Rooftop solar | 18 | 2 | 12 | 1 | 2 | 5 |
| Battery storage | 3 | 0 | 2 | 0 | 0 | 0.2 |
MW in pipeline: pending, approved and under-construction capacity.
How Bracknell Forest decides solar, wind and battery applications
Bracknell Forest has 5 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.
All projects in Bracknell Forest
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near GU47, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.