Energy Projects Near You

Solar, wind and battery projects near Wembley (HA0)

81 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of HA0 (Brent): 4 are waiting for a planning decision, 68 approved but not yet running, 3 operational. The largest live scheme is Mill Hill National Grid Substation (49.9 MW battery storage, approved on 13 March 2023, not yet built), 9.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

81projects within 10 km
4awaiting a decision
68approved, not running
3operational

Projects within 10 km of HA0

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Premier Park Road - Photovoltaic Systemrooftop solarrooftop solar1.4approved, not built may be out of dateupdated Mar 2022Mar 2022granted May 2022Mar 2022Brent2.8
Unit F, 6, Premier Park Roadrooftop solarrooftop solar1.3approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Brent2.8
Westfield London Shopping Centre, Ariel Wayrooftop solarrooftop solar1application submitted may be out of dateupdated Jul 2023Jun 2023—Jul 2023Hammersmith and Fulham7.5
Western International Marketrooftop solarrooftop solar1.7operationalupdated May 2016Jul 2015granted Sep 2015May 2016Hounslow9.4
Mill Hill National Grid Substationbattery storagebattery storage49.9approved, not builtupdated Mar 2023Sep 2020granted Mar 2023Mar 2023Barnet9.8
Smaller schemes under 1 MW, mostly rooftop solar (60)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Ark Elvin Academy, Cecil Avenuerooftop solarrooftop solar0.2approved, not builtupdated Jan 2024Jan 2024granted Mar 2024Jan 2024Brent1.0
Ealing Roadrooftop solarrooftop solar0.3approved, not builtupdated Dec 2025Sep 2025granted Nov 2025Dec 2025Brent1.4
Edwards Yard, Alperton - 581 Apartments & Commercial Unitsrooftop solarrooftop solar0.7approved, not builtupdated May 2022Sep 2020granted Jan 2022May 2022Brent1.5
Prop House, Abbey Roadrooftop solarrooftop solar0.6approved, not builtupdated Jan 2023Nov 2022granted Jan 2023Jan 2023Brent2.4
Tudor Estate, Abbey Roadrooftop solarrooftop solar—application submittedupdated May 2026Apr 2026—May 2026Brent2.5
Bestway Cash and Carry, Abbey Roadrooftop solarrooftop solar0.4approved, not builtMay 2026granted May 2026—Brent2.5
Premier Park Road, Unit Erooftop solarrooftop solar0.4approved, not builtupdated Jun 2023Mar 2023granted May 2023Jun 2023Brent2.6
Unit 6, Origin Business Park, Rainsford Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent2.6
Premier Park Road, Unit Crooftop solarrooftop solar0.5approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent2.6
Premier Park Road, Unit Brooftop solarrooftop solar0.6approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent2.7
Unit 5, Origin Business Park, Rainsford Roadrooftop solarrooftop solar0.6approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent2.7
Unit 2, Origin Business Park, Rainsford Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent2.7
David Lloyd Leisure Centrerooftop solarrooftop solar—approved, not builtupdated Nov 2025Jul 2025granted Oct 2025Nov 2025Ealing2.7
Unit 3, Origin Business Park, Rainsford Roadrooftop solarrooftop solar0.5approved, not builtupdated Jun 2023Mar 2023granted May 2023Jun 2023Ealing2.7
Unit 4, Origin Business Park, Rainsford Roadrooftop solarrooftop solar1approved, not builtupdated Jun 2023Mar 2023granted May 2023Jun 2023Brent2.8
Premier Park Road, Unit Arooftop solarrooftop solar0.4approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent2.8
Premier Park Road, Unit 4rooftop solarrooftop solar0.2approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent2.8
Premier Park Road, Unit 3rooftop solarrooftop solar0.6approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent2.8
Premier Park Road, Units 5-6rooftop solarrooftop solar0.4approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent2.8
Premier Park Road, Unit 9rooftop solarrooftop solar0.3approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent2.8
Premier Park Road, Unit 7-8rooftop solarrooftop solar0.4approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent2.8
Premier Park Road, Unit 1rooftop solarrooftop solar0.2approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent2.8
Premier Park, Park Royalrooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024Brent2.8
Premier Park Road, Units 10-11rooftop solarrooftop solar0.3approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent2.8
Unit 1, Origin Business Park, Rainsford Roadrooftop solarrooftop solar0.7approved, not builtupdated May 2023Mar 2023granted May 2023May 2023Brent2.8
Premier Park Road, Units 20-23rooftop solarrooftop solar0.4approved, not builtupdated Dec 2023Oct 2023granted Dec 2023Dec 2023Brent3.0
Prologis Greenford DC1, Oldfield Lane Northrooftop solarrooftop solar0.3application submitted may be out of dateupdated Apr 2024Mar 2024—Apr 2024Ealing3.1
Ikea Department Store, Drury Way Solar Pv Canopiessolar farmsolar farm0.7approved, not builtupdated Nov 2023Aug 2023granted Oct 2023Nov 2023Brent3.1
Nucleus, Central Wayrooftop solarrooftop solar0.3approved, not builtupdated Aug 2023Jul 2023granted Aug 2023Aug 2023Brent3.1
Nucleus, Central Wayrooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Aug 2023granted Oct 2023Nov 2023Brent3.2
Charlie Bighams, Mcnicol Driverooftop solarrooftop solar0.3approved, not builtupdated Jan 2024Dec 2023granted Feb 2024Jan 2024Brent3.2
Central Wayrooftop solarrooftop solar—approved, not builtupdated Jul 2025Apr 2025granted May 2025Jul 2025Brent3.3
Rock Building, Waxlow Roadrooftop solarrooftop solar0.4approved, not builtupdated Jan 2024Nov 2023granted Dec 2023Jan 2024Brent3.4
Light House, Western Roadrooftop solarrooftop solar0.4approved, not builtupdated Sep 2024Jul 2024granted Aug 2024Sep 2024Ealing3.6
Belazu Ingredient Company, Long Driverooftop solarrooftop solar0.3approved, not builtupdated Oct 2024Aug 2024granted Oct 2024Oct 2024Ealing3.7
Sergo Park Greenford Central, Phase 1A - Industrial, Warehouse & Officesrooftop solarrooftop solar0.4approved, not builtupdated Feb 2025Jul 2024granted Jan 2025Feb 2025Ealing4.0
St Georges Shopping Centre, St Anns Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2025Jan 2025granted Apr 2025May 2025Harrow4.1
University Of West London Solar Photovoltaic & Ground Source Heat Pumprooftop solarrooftop solar0.2application withdrawnupdated Dec 2021Jul 2021—Dec 2021Ealing4.9
University Of West London Solarrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Dec 2021Jul 2021granted Nov 2021Dec 2021Ealing4.9
Willesden Sports Centre, Donnington Roadrooftop solarrooftop solar0.3approved, not builtupdated Apr 2025Jan 2025granted Mar 2025Apr 2025Brent5.3
West Hendon Estate, Plots A, C & G - 350 Apartments & Commercial Unitsrooftop solarrooftop solar0.2approved, not builtupdated Mar 2025Apr 2023granted Aug 2024Mar 2025Barnet5.3
Kern House, Scrubs Lanerooftop solarrooftop solar—approved, not builtupdated Sep 2023Aug 2023granted Sep 2023Sep 2023Hammersmith and Fulham5.8
Hammersmith Hospital, Du Cane Roadrooftop solarrooftop solar0.2approved, not builtupdated Aug 2025Mar 2025granted Jul 2025Aug 2025Hammersmith and Fulham6.1
Phoenix Fitness Centre, Phoenix Closerooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Jan 2024granted Mar 2024Apr 2024Hammersmith and Fulham6.4
Headstone Lanerooftop solarrooftop solar0.6approved, not builtupdated Nov 2024Oct 2023refused Sep 2024Nov 2024Harrow6.4
Great Western Industrial Park, Armstrong Wayrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024Apr 2024granted Jun 2024Jul 2024Ealing6.4
Moberly Sports Centre - Photovoltaic Arraysrooftop solarrooftop solar0.2approved, not builtupdated Nov 2021Nov 2021granted Dec 2021Nov 2021Brent6.6
Moberly Sports Centre - Photovoltaic Arraysrooftop solarrooftop solar—refusedupdated Oct 2021Oct 2021refused Oct 2021Oct 2021Brent6.6
Brentford Works, Great West Road - Masterplanrooftop solarrooftop solar0.2approved, not builtupdated Jul 2026Nov 2024granted Jun 2026Jul 2026Hounslow6.7
Barnet Burnt Oak Leisure Centre, Watling Avenuerooftop solarrooftop solar0.2approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025Barnet6.9
Sainsburys Supermarkets, Essex Placerooftop solarrooftop solar0.3approved, not builtupdated Jul 2025May 2025granted Jul 2025Jul 2025Hounslow7.0
Shield Drive Industrial Estaterooftop solarrooftop solar—approved, not built may be out of dateupdated Sep 2022May 2022granted Jun 2022Sep 2022Hounslow7.2
Yeading Infant School, Carlyon Road Solar PV Systemsrooftop solarrooftop solar0.1application withdrawnupdated Sep 2024Jul 2024—Sep 2024Hillingdon7.2
Devonhurst Placerooftop solarrooftop solar—approved, not built may be out of dateupdated Apr 2022Mar 2022granted May 2022Apr 2022Hounslow7.2
West Cross Industrial Park Shield Driverooftop solarrooftop solar0.4approved, not builtupdated Nov 2023Aug 2023granted Oct 2023Nov 2023Hounslow7.4
Sainsburys, The Broadwayrooftop solarrooftop solar0.2refusedupdated Apr 2026Dec 2025refused Feb 2026Apr 2026Harrow7.4
Kensington Leisure Centre, Silchester Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Mar 2023Oct 2022granted Feb 2023Mar 2023Kensington and Chelsea7.4
Westfield London Shopping Centre, Ariel Wayrooftop solarrooftop solar0.3application submittedupdated Feb 2026Jan 2026—Feb 2026Hammersmith and Fulham7.5
Lombardy Retail Park, J Sainsbury Plcrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Nov 2024granted Jan 2025Jan 2025Hillingdon7.9
David Lloyd Leisurerooftop solarrooftop solar0.2refusedupdated Sep 2025Jul 2025refused Sep 2025Sep 2025Westminster8.2

16 more projects not listed (furthest or smallest).

Distance from the average position of the HA0 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm101000.7
Rooftop solar774661423.5
Battery storage3012049.9

MW in pipeline: pending, approved and under-construction capacity.

How Brent decides solar, wind and battery applications

ApplicationsBrentUK
Decided applications (solar, wind, battery)3910,236
Refused5 (13%)19%
Solar refused5 of 3912%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Brent

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near HA0, 10 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.