Mill Hill National Grid Substation (49.9 MW battery storage)

Mill Hill National Grid Substation is a 49.9 MW battery storage project in Barnet, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 March 2023, not yet built; the record was last updated on 27 March 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWbattery storage
approved, not builtstatus in REPD
27 March 2023record last updated
Barnetcouncil area

Planning timeline

DateStage
16 September 2020Application submitted
7 April 2022Refused by the planning authority
8 August 2022Appeal lodged
13 March 2023Planning permission granted
13 March 2023Appeal allowed

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
27 March 2023
Operator or applicant
Harbour Energy
Planning authority
Barnet
Planning application reference
20/4241/FUL
Appeal reference
22/00221/AREF
Address (REPD)
National Grid Mill Hill Substa, Partingdale Lane, Barnet,
Council area (by location)
Barnet
Time to decision
130 weeks
REPD reference
8009

Who decides

Barnet has 9 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Other large projects within 10 km

ProjectTypeMWStatuskm
Wrotham Parksolar farm30application submitted8.7
Land At Swanland Roadsolar farm5operational8.8
Hilfield Solar arrays & Battery storagesolar farm49.9application withdrawn9.8
Hilfield Lane, Aldenhambattery storage170approved, not built9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6176, -0.2114).