Wrotham Park (30 MW solar farm)

Wrotham Park is a 30 MW solar farm project in Hertsmere, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 18 July 2025, no decision recorded; the record was last updated on 29 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWsolar farm
application submittedstatus in REPD
29 August 2025record last updated
Hertsmerecouncil area

Planning timeline

DateStage
18 July 2025Application submitted

Project details

Technology
solar farm
Capacity
30 MW
Status (REPD)
application submitted
Record last updated
29 August 2025
Operator or applicant
Enviromena
Planning authority
Hertsmere
Planning application reference
25/1023/FUL
Site area
39.6 ha
Address (REPD)
N/O Earls Lane, South Mimms, Potters Bar
Council area (by location)
Hertsmere
Name in REPD
Wrotham Park - Solar Panels
REPD reference
19077

Who decides

ApplicationsHertsmereUK
Decided applications (solar, wind, battery)1610,236
Refused4 (25%)19%
Solar refused2 of 1312%
Battery storage refused2 of 316%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed4 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land At Swanland Roadsolar farm5operational1.3
Potters Bar Solar Farmsolar farm5operational3.0
Tollgate Farm, Welham Green Solar Farmsolar farm16application submitted4.5
Tollgate Farm Battery Storagebattery storage49.5under construction4.6
Dellsome Power Hatfield Grid Station Energy storage facilitybattery storage5approved, not built4.7
Butterfly Lane, Elstree BESSbattery storage99.9appeal lodged5.4
Hilfield Solar arrays & Battery storagesolar farm49.9application withdrawn7.8
Elstree Substation, Hilfield Lanebattery storage400application withdrawn7.9
Hilfield Lane, Aldenhambattery storage170approved, not built8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6938, -0.241).