Land At Swanland Road (5 MW solar farm)

Land At Swanland Road is a 5 MW solar farm project in Hertsmere, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 March 2017; the record was last updated on 19 July 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
19 July 2017record last updated
Hertsmerecouncil area

Planning timeline

DateStage
28 May 2015Application submitted
7 January 2016Planning permission granted
3 January 2017Construction started
23 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
19 July 2017
Operator or applicant
Gascoyne Holdings
Planning authority
Hertsmere
Planning application reference
15/0784/FUL
Site area
8.1 ha
Address (REPD)
Land At, Swanland Road, South Mimms, Potters Bar
Council area (by location)
Hertsmere
Time to decision
32 weeks
REPD reference
5295

Who decides

ApplicationsHertsmereUK
Decided applications (solar, wind, battery)1610,236
Refused4 (25%)19%
Solar refused2 of 1312%
Battery storage refused2 of 316%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed4 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Wrotham Parksolar farm30application submitted1.3
Potters Bar Solar Farmsolar farm5operational1.8
Tollgate Farm Battery Storagebattery storage49.5under construction4.4
Tollgate Farm, Welham Green Solar Farmsolar farm16application submitted4.5
Dellsome Power Hatfield Grid Station Energy storage facilitybattery storage5approved, not built4.6
Butterfly Lane, Elstree BESSbattery storage99.9appeal lodged6.7
Mill Hill National Grid Substationbattery storage49.9approved, not built8.8
Hilfield Solar arrays & Battery storagesolar farm49.9application withdrawn9.1
Elstree Substation, Hilfield Lanebattery storage400application withdrawn9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6966, -0.2221).