Solar, wind and battery projects near Potters Bar (EN6)
36 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of EN6 (Hertsmere): 5 are waiting for a planning decision, 25 approved but not yet running, 4 operational. The largest live scheme is Butterfly Lane, Elstree BESS (99.9 MW battery storage, refused; appeal lodged on 31 March 2026), 9.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of EN6
Projects of 1 MW and more (15)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Potters Bar Solar Farmsolar farm | solar farm | 5 | operationalupdated May 2017 | Sep 2015 | granted Dec 2015 | May 2017 | Hertsmere | 2.3 |
| Land At Swanland Roadsolar farm | solar farm | 5 | operationalupdated Jul 2017 | May 2015 | granted Jan 2016 | Jul 2017 | Hertsmere | 3.2 |
| Wrotham Parksolar farm | solar farm | 30 | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 | Hertsmere | 4.5 |
| Tollgate Farm Battery Storagebattery storage | battery storage | 49.5 | under constructionupdated Feb 2022 | Oct 2017 | granted Jan 2019 | Feb 2022 | Welwyn Hatfield | 5.8 |
| Dellsome Power Hatfield Grid Station Energy storage facilitybattery storage | battery storage | 5 | approved, not built may be out of dateupdated May 2021 | Apr 2021 | granted Jul 2021 | May 2021 | Welwyn Hatfield | 6.0 |
| Tollgate Farm, Welham Green Solar Farmsolar farm | solar farm | 16 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Welwyn Hatfield | 6.1 |
| Bell Lane Solar Farmsolar farm | solar farm | 1 | refusedupdated Dec 2015 | Aug 2015 | refused Nov 2015 | Dec 2015 | Hertsmere | 7.7 |
| Elstree Film And TV Studios, Shenley Roadrooftop solar | rooftop solar | 3 | operationalupdated Sep 2023 | Feb 2023 | — | Sep 2023 | Hertsmere | 8.0 |
| St Marys C Of E Va High School, Lieutenant Ellis Wayrooftop solar | rooftop solar | 8.8 | approved, not builtupdated Jul 2025 | May 2025 | granted Jul 2025 | Jul 2025 | Broxbourne | 8.4 |
| Gypsy Moth Avenuerooftop solar | rooftop solar | 1.2 | approved, not built may be out of dateupdated Apr 2022 | Mar 2022 | granted Aug 2022 | Apr 2022 | Welwyn Hatfield | 9.2 |
| Mill Hill National Grid Substationbattery storage | battery storage | 49.9 | approved, not builtupdated Mar 2023 | Sep 2020 | granted Mar 2023 | Mar 2023 | Barnet | 9.4 |
| Stanborough, Hatfieldsolar farm | solar farm | 10 | approved, not builtupdated May 2025 | Aug 2023 | granted Sep 2024 | May 2025 | Welwyn Hatfield | 9.5 |
| Stanborough, Hatfieldbattery storage | battery storage | 1.5 | approved, not builtupdated May 2025 | Aug 2023 | granted Sep 2024 | May 2025 | Welwyn Hatfield | 9.5 |
| Computacenter Warehouserooftop solar | rooftop solar | 2 | under constructionupdated Nov 2019 | Jan 2019 | granted Mar 2019 | Nov 2019 | Welwyn Hatfield | 9.6 |
| Butterfly Lane, Elstree BESSbattery storage | battery storage | 99.9 | appeal lodgedupdated Jun 2026 | Jul 2025 | — | Jun 2026 | Hertsmere | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (21)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Queenswood School, Shepherds Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2023 | May 2023 | granted Aug 2023 | Aug 2023 | Welwyn Hatfield | 1.8 |
| Multi Storage, Cranborne Industrial Estaterooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2023 | Mar 2023 | granted Apr 2023 | May 2023 | Hertsmere | 2.2 |
| Blanche Lane, South Mimmsrooftop solar | rooftop solar | 0.6 | under constructionupdated Jun 2022 | Jun 2022 | granted Aug 2023 | Jun 2022 | Hertsmere | 4.6 |
| NIBSC, Blanche Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Dec 2023 | Dec 2023 | Hertsmere | 4.6 |
| Welham Greenrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2022 | Jun 2022 | granted Aug 2022 | Jun 2022 | Welwyn Hatfield | 5.0 |
| The Totteridge Academy, Barnet Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Barnet | 7.0 |
| Unit 2, York Crescentrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Dec 2022 | Oct 2022 | granted Nov 2022 | Dec 2022 | Hertsmere | 7.0 |
| North London Ad Plant, Coursers Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2024 | Jul 2024 | granted Aug 2024 | Sep 2024 | Hertsmere | 7.5 |
| Willows Activity Farm, Colney Heathrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2022 | Mar 2022 | granted May 2022 | Apr 2022 | Hertsmere | 7.5 |
| Sainsburys Supermarketsrooftop solar | rooftop solar | 0.6 | approved, not builtupdated May 2026 | Feb 2026 | granted Apr 2026 | May 2026 | St Albans | 7.6 |
| Ashmole Academy, Cecil Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2026 | Mar 2026 | granted May 2026 | Jun 2026 | Barnet | 7.9 |
| Elstree Film And TV Studios, Shenley Road Solar Panels And ASHPsrooftop solar | rooftop solar | — | application withdrawnupdated May 2023 | Feb 2022 | — | May 2023 | Hertsmere | 8.0 |
| Enfield County School For Girls, Holly Walkrooftop solar | rooftop solar | 0.2 | application submitted | May 2026 | — | — | Enfield | 8.1 |
| Mill Hill County High School, Worcester Crescentrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2023 | Aug 2023 | granted Sep 2023 | Oct 2023 | Barnet | 9.2 |
| Friern Barnet School, Hemington Avenuerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2025 | Feb 2025 | granted Jul 2025 | Aug 2025 | Barnet | 9.4 |
| Sainsburys Supermarkets, Green Lanesrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2025 | Feb 2025 | granted Apr 2025 | Mar 2025 | Enfield | 9.4 |
| Sainsburys Supermarketsrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Apr 2025 | Jan 2025 | granted Mar 2025 | Apr 2025 | Enfield | 9.7 |
| The Albert Bygrave Retail Park, North Orbital Roadrooftop solar | rooftop solar | — | approved, not builtupdated Feb 2026 | Nov 2025 | granted Jan 2026 | Feb 2026 | St Albans | 9.7 |
| Chalkmill Driverooftop solar | rooftop solar | 0.5 | application submitted | May 2026 | — | — | Enfield | 9.8 |
| Aylett Nurseriesrooftop solar | rooftop solar | — | operationalupdated Aug 2023 | — | — | Aug 2023 | St Albans | 9.8 |
| Edmonton lower schoolrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Mar 2024 | Mar 2024 | Enfield | 10.0 |
Distance from the average position of the EN6 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 6 | 2 | 1 | 2 | 1 | 56 |
| Rooftop solar | 25 | 2 | 20 | 2 | 0 | 17.3 |
| Battery storage | 5 | 1 | 4 | 0 | 0 | 206 |
MW in pipeline: pending, approved and under-construction capacity.
How Hertsmere decides solar, wind and battery applications
| Applications | Hertsmere | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 16 | 10,236 |
| Refused | 4 (25%) | 19% |
| Solar refused | 2 of 13 | 12% |
| Battery storage refused | 2 of 3 | 16% |
| Median time from submission to decision | 11.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near EN6, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.