Energy Projects Near You

Renewable energy projects in Hertsmere

20 solar, wind or battery projects of 150 kW or more are located in Hertsmere (REPD, July 2026 extract): 2 pending, 10 approved but not running, 3 operational and 1 refused. The council refused 4 of 16 decided applications (25%; UK 19%), with a median 11 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20projects in the council area
2awaiting a decision
10approved, not running
25%of decisions refused

How Hertsmere decides

ApplicationsHertsmereUK
Decided applications (solar, wind, battery)1610,236
Refused4 (25%)19%
Solar refused2 of 1312%
Battery storage refused2 of 316%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed4 / 1—

Projects in Hertsmere

Projects of 1 MW and more (9)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Elstree Substation, Hilfield Lanebattery storagebattery storage400application withdrawnupdated Nov 2024Nov 2023—Nov 2024
Hilfield Lane, Aldenhambattery storagebattery storage170approved, not builtupdated Feb 2026Feb 2025granted Jan 2026Feb 2026
Butterfly Lane, Elstree BESSbattery storagebattery storage99.9appeal lodgedupdated Jun 2026Jul 2025—Jun 2026
Hilfield Solar arrays & Battery storagesolar farmsolar farm49.9application withdrawnupdated Jul 2024May 2022—Jul 2024
Wrotham Parksolar farmsolar farm30application submittedupdated Aug 2025Jul 2025—Aug 2025
Land At Swanland Roadsolar farmsolar farm5operationalupdated Jul 2017May 2015granted Jan 2016Jul 2017
Potters Bar Solar Farmsolar farmsolar farm5operationalupdated May 2017Sep 2015granted Dec 2015May 2017
Elstree Film And TV Studios, Shenley Roadrooftop solarrooftop solar3operationalupdated Sep 2023Feb 2023—Sep 2023
Bell Lane Solar Farmsolar farmsolar farm1refusedupdated Dec 2015Aug 2015refused Nov 2015Dec 2015
Smaller schemes under 1 MW, mostly rooftop solar (11)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Blanche Lane, South Mimmsrooftop solarrooftop solar0.6under constructionupdated Jun 2022Jun 2022granted Aug 2023Jun 2022
C P House, Otterspool Wayrooftop solarrooftop solar0.3approved, not builtupdated Dec 2022Oct 2022granted Dec 2022Dec 2022
David Lloyd Leisure Club, Hartspring Lanerooftop solarrooftop solar0.3approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025
Unit 2, York Crescentrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Dec 2022Oct 2022granted Nov 2022Dec 2022
NIBSC, Blanche Lanerooftop solarrooftop solar0.2approved, not builtupdated Dec 2023Oct 2023granted Dec 2023Dec 2023
Willows Activity Farm, Colney Heathrooftop solarrooftop solar0.2approved, not builtupdated Apr 2022Mar 2022granted May 2022Apr 2022
North London Ad Plant, Coursers Roadrooftop solarrooftop solar0.2approved, not builtupdated Sep 2024Jul 2024granted Aug 2024Sep 2024
Centennial Park, Centennial Avenuerooftop solarrooftop solar0.2approved, not builtupdated Mar 2025Dec 2024granted Feb 2025Mar 2025
Multi Storage, Cranborne Industrial Estaterooftop solarrooftop solar0.2approved, not builtupdated May 2023Mar 2023granted Apr 2023May 2023
Hilfield Solar arrays & Battery storagebattery storagebattery storage—application withdrawnupdated Jul 2024May 2022—Jul 2024
Elstree Film And TV Studios, Shenley Road Solar Panels And ASHPsrooftop solarrooftop solar—application withdrawnupdated May 2023Feb 2022—May 2023

Postcode districts in Hertsmere

DistrictProjects within 10 kmPendingApprovedOperational
EN6365254
WD6443285
WD7466275
WD23355183

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Hertsmere by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.