Tollgate Farm Battery Storage (49.5 MW)

Tollgate Farm Battery Storage is a 49.5 MW battery storage project in Welwyn Hatfield, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 February 2022; the record was last updated on 1 February 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.5 MWbattery storage
under constructionstatus in REPD
1 February 2022record last updated
Welwyn Hatfieldcouncil area

Planning timeline

DateStage
12 October 2017Application submitted
22 January 2019Planning permission granted
1 February 2022Construction started

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.5 MW
Status (REPD)
under construction
Record last updated
1 February 2022
Operator or applicant
RNA Energy / Harmony Energy Storage/ Tag Energy UK
Planning authority
Welwyn Hatfield
Planning application reference
6/2017/2340/FULL
Address (REPD)
Tollgate Farm, Tollgate Road, North Mymms
Council area (by location)
Welwyn Hatfield
Time to decision
67 weeks
REPD reference
7335

Earlier applications for this site

ApplicationMWSubmittedOutcome
Tollgate Battery Storage Facility 6/2017/0702/MAJ49.56 April 2017refused 6 July 2017

Who decides

ApplicationsWelwyn HatfieldUK
Decided applications (solar, wind, battery)1510,236
Refused2 (13%)19%
Solar refused1 of 812%
Battery storage refused1 of 716%
Median time from submission to decision11.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Dellsome Power Hatfield Grid Station Energy storage facilitybattery storage5approved, not built0.2
Tollgate Farm, Welham Green Solar Farmsolar farm16application submitted0.5
Potters Bar Solar Farmsolar farm5operational3.6
Land At Swanland Roadsolar farm5operational4.4
Wrotham Parksolar farm30application submitted4.6
Stanborough, Hatfieldsolar farm10approved, not built5.2
Butterfly Lane, Elstree BESSbattery storage99.9appeal lodged8.0
Welwyn Power Energy Storage Facilitybattery storage5approved, not built8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7352, -0.2372).