Energy Projects Near You

Stanborough, Hatfield (10 MW solar farm)

Stanborough, Hatfield is a 10 MW solar farm project in Welwyn Hatfield, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 16 September 2024, not yet built; the record was last updated on 12 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
approved, not builtstatus in REPD
12 May 2025record last updated
Welwyn Hatfieldcouncil area

Planning timeline

DateStage
29 August 2023Application submitted
16 September 2024Planning permission granted
16 September 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
approved, not built
Record last updated
12 May 2025
Operator or applicant
J Reddington Limited
Planning authority
Welwyn Hatfield
Planning application reference
6/2023/1802/MAJ
Site area
9.1 ha
Address (REPD)
Land East of A6129 Stanborough Hatfield
Council area (by location)
Welwyn Hatfield
Time to decision
55 weeks
Name in REPD
Stanborough, Hatfield - Solar Array
REPD reference
14878

The scheme also includes 1.5 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsWelwyn HatfieldUK
Decided applications (solar, wind, battery)1510,236
Refused2 (13%)19%
Solar refused1 of 812%
Battery storage refused1 of 716%
Median time from submission to decision11.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Welwyn Power Energy Storage Facilitybattery storage5approved, not built2.9
Dellsome Power Hatfield Grid Station Energy storage facilitybattery storage5approved, not built5.1
Tollgate Farm Battery Storagebattery storage49.5under construction5.2
Tollgate Farm, Welham Green Solar Farmsolar farm16application submitted5.4
Potters Bar Solar Farmsolar farm5operational8.1
Land At Swanland Roadsolar farm5operational9.4
Three Houses Lanesolar farm11.3refused9.6
Swangleys Farmsolar farm8.5application withdrawn9.6
Wrotham Parksolar farm30application submitted9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7809, -0.22).