Energy Projects Near You

Three Houses Lane (11.3 MW solar farm)

Three Houses Lane is an 11.3 MW solar farm project in North Hertfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 31 October 2016; the record was last updated on 28 February 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11.3 MWsolar farm
refusedstatus in REPD
28 February 2017record last updated
North Hertfordshirecouncil area

Planning timeline

DateStage
10 September 2014Application submitted
27 July 2015Secretary of State intervened
31 October 2016Refused by the planning authority
31 October 2016Secretary of State refused

Project details

Technology
solar farm
Capacity
11.3 MW
Status (REPD)
refused
Record last updated
28 February 2017
Operator or applicant
Lightsource Renewable Energy
Planning authority
North Hertfordshire
Planning application reference
14/02360/1
Site area
22.2 ha
Address (REPD)
Land adjacent to, Three Houses Lane, Codicote
Council area (by location)
North Hertfordshire
Time to decision
112 weeks
REPD reference
2275

Who decides

ApplicationsNorth HertfordshireUK
Decided applications (solar, wind, battery)1710,236
Refused5 (29%)19%
Solar refused3 of 912%
Onshore wind refused1 of 145%
Battery storage refused1 of 716%
Median time from submission to decision88.4 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Rush Green Motorsbattery storage50application withdrawn3.7
Swangleys Farmsolar farm8.5application withdrawn4.7
St Ippolyts Solar Farm & Battery Storagebattery storage12.5approved, not built6.4
St Ippolyts Solar Farm & Battery Storagesolar farm25approved, not built6.4
Stevenage Road, Titmore Greenbattery storage57application submitted6.6
Land North of Chiltern Greeensolar farm5operational7.3
Ld At Lawrence End Park &, Dane Streetsolar farm5operational7.8
Welwyn Power Energy Storage Facilitybattery storage5approved, not built7.8
Wandon End Solar Farm & Battery Storagesolar farm49.9approved, not built8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8658, -0.2454).