Wandon End Solar Farm & Battery Storage (49.9 MW)

Wandon End Solar Farm & Battery Storage is a 49.9 MW solar farm project in North Hertfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 July 2025, not yet built; the record was last updated on 29 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
29 July 2025record last updated
North Hertfordshirecouncil area

Planning timeline

DateStage
5 January 2023Application submitted
15 July 2025Planning permission granted
15 July 2025Appeal allowed
15 July 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
29 July 2025
Operator or applicant
EPL 002 Limited
Planning authority
North Hertfordshire
Planning application reference
22/03231/FP
Site area
106.0 ha
Address (REPD)
Ne/O Wandon End, Luton
Council area (by location)
North Hertfordshire
Time to decision
132 weeks
Name in REPD
Wandon End - Solar Farm & Battery Storage
REPD reference
13055

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsNorth HertfordshireUK
Decided applications (solar, wind, battery)1710,236
Refused5 (29%)19%
Solar refused3 of 912%
Onshore wind refused1 of 145%
Battery storage refused1 of 716%
Median time from submission to decision88.4 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ld At Lawrence End Park &, Dane Streetsolar farm5operational2.5
Land North of Chiltern Greeensolar farm5operational3.8
Chiltern Green Roadsolar farm10application withdrawn4.0
Rush Green Motorsbattery storage50application withdrawn7.5
St Ippolyts Solar Farm & Battery Storagebattery storage12.5approved, not built7.7
St Ippolyts Solar Farm & Battery Storagesolar farm25approved, not built7.7
Three Houses Lanesolar farm11.3refused8.0
Stevenage Road, Titmore Greenbattery storage57application submitted8.4
Vauxhall Motorsrooftop solar5abandoned9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8958, -0.3511).