Chiltern Green Road (10 MW solar farm)

Chiltern Green Road is a 10 MW solar farm project in Central Bedfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 30 June 2015; the record was last updated on 16 August 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
application withdrawnstatus in REPD
16 August 2017record last updated
Central Bedfordshirecouncil area

Planning timeline

DateStage
1 April 2015Application submitted
30 June 2015Application withdrawn

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
application withdrawn
Record last updated
16 August 2017
Operator or applicant
Lightsource Renewable Energy
Planning authority
Central Bedfordshire
Planning application reference
CB/15/01285/FULL
Site area
22.3 ha
Council area (by location)
Central Bedfordshire
REPD reference
1935

Who decides

ApplicationsCentral BedfordshireUK
Decided applications (solar, wind, battery)5910,236
Refused8 (14%)19%
Solar refused4 of 3612%
Onshore wind refused2 of 745%
Battery storage refused2 of 1616%
Median time from submission to decision19.6 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land North of Chiltern Greeensolar farm5operational0.8
Ld At Lawrence End Park &, Dane Streetsolar farm5operational1.5
Wandon End Solar Farm & Battery Storagesolar farm49.9approved, not built4.0
Caddington Solar Farm (Phase 2)solar farm5operational7.3
Three Houses Lanesolar farm11.3refused8.1
Watling Street, Caddington Solar Farmsolar farm19.7approved, not built8.2
Rush Green Motorsbattery storage50application withdrawn9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8606, -0.363).