Energy Projects Near You

Land North of Chiltern Greeen (5 MW solar farm)

Land North of Chiltern Greeen is a 5 MW solar farm project in Central Bedfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 10 March 2016; the record was last updated on 20 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
20 May 2016record last updated
Central Bedfordshirecouncil area

Planning timeline

DateStage
27 March 2015Application submitted
26 June 2015Planning permission granted
10 January 2016Construction started
10 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
20 May 2016
Operator or applicant
Lightsource Renewable Energy
Planning authority
Central Bedfordshire
Planning application reference
CB/15/01204/FULL
Site area
13.1 ha
Address (REPD)
Land North of Chiltern Green F, Lawrence End Park North Herts, Chiltern Green, Luton, Bedfordshire
Council area (by location)
Central Bedfordshire
Time to decision
13 weeks
REPD reference
5162

Who decides

ApplicationsCentral BedfordshireUK
Decided applications (solar, wind, battery)5910,236
Refused8 (14%)19%
Solar refused4 of 3612%
Onshore wind refused2 of 745%
Battery storage refused2 of 1616%
Median time from submission to decision19.6 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Chiltern Green Roadsolar farm10application withdrawn0.8
Ld At Lawrence End Park &, Dane Streetsolar farm5operational1.4
Wandon End Solar Farm & Battery Storagesolar farm49.9approved, not built3.8
Three Houses Lanesolar farm11.3refused7.3
Caddington Solar Farm (Phase 2)solar farm5operational8.0
Rush Green Motorsbattery storage50application withdrawn8.6
Watling Street, Caddington Solar Farmsolar farm19.7approved, not built8.9
St Ippolyts Solar Farm & Battery Storagesolar farm25approved, not built9.9
St Ippolyts Solar Farm & Battery Storagebattery storage12.5approved, not built9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8617, -0.352).