St Ippolyts Solar Farm & Battery Storage (25 MW)

St Ippolyts Solar Farm & Battery Storage is a 25 MW solar farm project in North Hertfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 28 July 2025, not yet built; the record was last updated on 22 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWsolar farm
approved, not builtstatus in REPD
22 August 2025record last updated
North Hertfordshirecouncil area

Planning timeline

DateStage
29 July 2021Application submitted
28 July 2025Planning permission granted
28 July 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
25 MW
Status (REPD)
approved, not built
Record last updated
22 August 2025
Operator or applicant
Brockwell Storage & Solar Limited
Planning authority
North Hertfordshire
Planning application reference
24/02455/FP
Site area
35.5 ha
Address (REPD)
Opp Wymondley Grid Station & To The S/O Sperberry Hill, St Ippolyts, Hitchin
Council area (by location)
North Hertfordshire
Time to decision
209 weeks
Name in REPD
St Ippolyts - Solar Farm & Battery Storage
REPD reference
17445

The scheme also includes 25 MW of solar farm, recorded separately in REPD (replaced by a revised application).

Earlier applications for this site

ApplicationMWSubmittedOutcome
Strevenage Road Solar Farm 15/01532/1518 June 2015refused 24 February 2016
St Ippolyts Solar Farm & Battery Storage 22/00709/FP2513 March 2022refused 22 November 2023

Who decides

ApplicationsNorth HertfordshireUK
Decided applications (solar, wind, battery)1710,236
Refused5 (29%)19%
Solar refused3 of 912%
Onshore wind refused1 of 145%
Battery storage refused1 of 716%
Median time from submission to decision88.4 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
St Ippolyts Solar Farm & Battery Storagebattery storage12.5approved, not built<0.1
Stevenage Road, Titmore Greenbattery storage57application submitted0.6
Wymondley Solar Farm, Great Wymondleysolar farm50approved, not built2.2
Rush Green Motorsbattery storage50application withdrawn2.7
Three Houses Lanesolar farm11.3refused6.4
Weston Hillswind farm6refused7.1
Westonwind farm6application withdrawn7.2
Letchworth Garden City - Urban Reserve Energy Storage Facilitybattery storage5approved, not built7.2
Wandon End Solar Farm & Battery Storagesolar farm49.9approved, not built7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9229, -0.2473).