Solar, wind and battery projects near Knebworth (SG3)

32 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SG3 (North Hertfordshire): 3 are waiting for a planning decision, 23 approved but not yet running, 1 operational. The largest live scheme is Stevenage Road, Titmore Green (57 MW battery storage, application submitted on 20 May 2025, no decision recorded), 8.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

32projects within 10 km
3awaiting a decision
23approved, not running
1operational

Projects within 10 km of SG3

Projects of 1 MW and more (16)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Swangleys Farmsolar farmsolar farm8.5application withdrawnupdated Aug 2018Aug 2014—Aug 2018North Hertfordshire0.5
High Elms Lane Turbinewind turbinewind turbine2refusedupdated Mar 2012Jul 2011refused Oct 2011Mar 2012East Hertfordshire4.3
Three Houses Lanesolar farmsolar farm11.3refusedupdated Feb 2017Sep 2014refused Oct 2016Feb 2017North Hertfordshire4.4
Benington Wind Farmwind farmwind farm6.8refusedupdated May 2009May 2008refused Jan 2009May 2009East Hertfordshire5.0
Flamingo Houserooftop solarrooftop solar1operationalupdated Dec 2020Apr 2019granted Oct 2019Dec 2020Stevenage5.5
Rush Green Motorsbattery storagebattery storage50application withdrawnupdated Apr 2025Feb 2024—Apr 2025North Hertfordshire5.9
Welwyn Power Energy Storage Facilitybattery storagebattery storage5approved, not built may be out of dateupdated Jun 2022May 2022granted Aug 2022Jun 2022Welwyn Hatfield6.5
Stevenage Road, Titmore Greenbattery storagebattery storage57application submittedupdated Aug 2025May 2025—Aug 2025North Hertfordshire8.1
St Ippolyts Solar Farm & Battery Storagesolar farmsolar farm25approved, not builtupdated Aug 2025Jul 2021granted Jul 2025Aug 2025North Hertfordshire8.3
St Ippolyts Solar Farm & Battery Storagebattery storagebattery storage12.5approved, not builtupdated Aug 2025Jul 2021granted Jul 2025Aug 2025North Hertfordshire8.3
Stanborough, Hatfieldsolar farmsolar farm10approved, not builtupdated May 2025Aug 2023granted Sep 2024May 2025Welwyn Hatfield9.2
Stanborough, Hatfieldbattery storagebattery storage1.5approved, not builtupdated May 2025Aug 2023granted Sep 2024May 2025Welwyn Hatfield9.2
Westmill Quarry, Westmill Road Solar Farmsolar farmsolar farm7.3application submitted may be out of dateupdated Sep 2023Sep 2023—Sep 2023East Hertfordshire9.4
Wymondley Solar Farm, Great Wymondleysolar farmsolar farm50approved, not builtupdated Feb 2026Dec 2021—Feb 2026North Hertfordshire9.8
Solar Farm & Battery Energy Storagesolar farmsolar farm24approved, not builtupdated Dec 2025Jul 2024granted Oct 2025Dec 2025East Hertfordshire10.0
Solar Farm & Battery Energy Storagebattery storagebattery storage5approved, not builtupdated Dec 2025Jul 2024granted Oct 2025Dec 2025East Hertfordshire10.0
Smaller schemes under 1 MW, mostly rooftop solar (16)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Unit 1, Roebuck Retail Park, London Roadrooftop solarrooftop solar0.2approved, not builtupdated Aug 2025Jun 2025granted Jul 2025Aug 2025Stevenage3.2
Roaring Meg Retail Park, London Roadrooftop solarrooftop solar0.3approved, not builtupdated Mar 2023Jan 2023granted Mar 2023Mar 2023Stevenage3.7
Stevenage Leisure Park, Kings Wayrooftop solarrooftop solar0.2approved, not builtupdated Feb 2022Feb 2022granted Apr 2022Feb 2022Stevenage4.7
David Lloyd Fitness Centre, Kings Wayrooftop solarrooftop solar—approved, not builtupdated Aug 2023Jun 2023granted Jul 2023Aug 2023Stevenage4.7
Aston End - Ground Mounted Solar Panelssolar farmsolar farm0.2approved, not builtupdated May 2026Jul 2025granted Mar 2026May 2026Stevenage4.9
Tesco Extra, The Forumrooftop solarrooftop solar0.3approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026Stevenage5.1
Tesco Store The Forum Stevenagerooftop solarrooftop solar0.4approved, not builtupdated Feb 2023Jan 2020granted Mar 2020Feb 2023Stevenage5.1
Larwood Drive, Rusling Way - Micro Battery Storagebattery storagebattery storage0.2application submittedMay 2026——Stevenage5.7
Nobel Secondary School, Mobbsbury Waybattery storagebattery storage0.2approved, not built may be out of dateupdated Mar 2023Jan 2023granted Mar 2023Mar 2023Stevenage5.8
Brownfieldsbattery storagebattery storage0.2approved, not builtupdated Oct 2023Aug 2023granted Sep 2023Oct 2023Welwyn Hatfield6.3
Martins Way - Micro Energy Storagebattery storagebattery storage0.2approved, not builtApr 2026granted Jun 2026—Stevenage6.6
Ridgeway Academy, Herns Lanerooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Welwyn Hatfield6.6
Morrisons Supermarketrooftop solarrooftop solar0.3approved, not builtupdated Oct 2024Aug 2024granted Oct 2024Oct 2024Welwyn Hatfield6.8
Sainsburys, Hitchin Roadrooftop solarrooftop solar0.3approved, not builtupdated Apr 2025Jan 2025granted Mar 2025Apr 2025Stevenage7.0
Verge In Highway, Great North Roadbattery storagebattery storage0.2approved, not builtupdated Mar 2026Sep 2025granted Nov 2025Mar 2026Welwyn Hatfield8.5
Wymondley Solar Farm, Great Wymondleybattery storagebattery storage—approved, not builtupdated Feb 2026Dec 2021—Feb 2026North Hertfordshire9.8

Distance from the average position of the SG3 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm81501117
Rooftop solar1009102.1
Wind farm100010
Wind turbine100010
Battery storage12290082

MW in pipeline: pending, approved and under-construction capacity.

How North Hertfordshire decides solar, wind and battery applications

ApplicationsNorth HertfordshireUK
Decided applications (solar, wind, battery)1710,236
Refused5 (29%)19%
Solar refused3 of 912%
Onshore wind refused1 of 145%
Battery storage refused1 of 716%
Median time from submission to decision88.4 weeks17.0 weeks
Appeals lodged / allowed1 / 2—

All projects in North Hertfordshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SG3, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.