Energy Projects Near You

Westmill Quarry, Westmill Road Solar Farm (7.3 MW)

Westmill Quarry, Westmill Road Solar Farm is a 7.3 MW solar farm project in East Hertfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 1 September 2023, no decision recorded; the record was last updated on 22 September 2023. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.3 MWsolar farm
application submittedmay be out of datestatus in REPD
22 September 2023record last updated
East Hertfordshirecouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
1 September 2023Application submitted

Project details

Technology
solar farm
Capacity
7.3 MW
Status (REPD)
application submitted
Record last updated
22 September 2023
Operator or applicant
Biffa Waste Services Limited
Planning authority
East Hertfordshire
Planning application reference
PL/0357/23
Site area
10.4 ha
Address (REPD)
Westmill Quarry, Westmill Road
Council area (by location)
East Hertfordshire
Name in REPD
Westmill Quarry, Westmill Road - Solar Farm
REPD reference
13928

Who decides

ApplicationsEast HertfordshireUK
Decided applications (solar, wind, battery)2010,236
Refused7 (35%)19%
Solar refused4 of 1312%
Onshore wind refused2 of 245%
Battery storage refused1 of 516%
Median time from submission to decision22.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Solar Farm & Battery Energy Storagebattery storage5approved, not built1.5
Solar Farm & Battery Energy Storagesolar farm24approved, not built1.5
Broxbournebury Solar Fieldsolar farm5permission expired8.5
Benington Wind Farmwind farm6.8refused9.0
Mill Farmsolar farm5operational9.1
Swangleys Farmsolar farm8.5application withdrawn9.2
East End Solar Farmsolar farm49.9approved, not built9.3
Welwyn Power Energy Storage Facilitybattery storage5approved, not built9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8259, -0.058).