Broxbournebury Solar Field (5 MW)

Broxbournebury Solar Field is a 5 MW solar farm project in Broxbourne, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 15 February 2019; the record was last updated on 27 August 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
permission expiredstatus in REPD
27 August 2019record last updated
Broxbournecouncil area

Planning timeline

DateStage
15 September 2015Application submitted
15 February 2016Planning permission granted
15 February 2019Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
permission expired
Record last updated
27 August 2019
Operator or applicant
Mulbrick Clean Energy
Planning authority
Broxbourne
Planning application reference
07/15/0866/F
Site area
9.1 ha
Address (REPD)
Land Adjacent to Cock Lane, Hoddesdon
Council area (by location)
Broxbourne
Time to decision
22 weeks
REPD reference
5647

Who decides

Broxbourne has 4 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Other large projects within 10 km

ProjectTypeMWStatuskm
East End Solar Farmsolar farm49.9approved, not built5.8
St Marys C Of E Va High School, Lieutenant Ellis Wayrooftop solar8.8approved, not built6.2
Solar Farm & Battery Energy Storagebattery storage5approved, not built7.0
Solar Farm & Battery Energy Storagesolar farm24approved, not built7.0
Westmill Quarry, Westmill Road Solar Farmsolar farm7.3application submitted8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7507, -0.0357).