Energy Projects Near You

Solar, wind and battery projects near Hertford (SG14)

20 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SG14 (East Hertfordshire): 1 is waiting for a planning decision, 13 approved but not yet running. The largest live scheme is Solar Farm & Battery Energy Storage (24 MW solar farm, approved on 17 October 2025, not yet built), 2.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20projects within 10 km
1awaiting a decision
13approved, not running
0operational

Projects within 10 km of SG14

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Solar Farm & Battery Energy Storagesolar farmsolar farm24approved, not builtupdated Dec 2025Jul 2024granted Oct 2025Dec 2025East Hertfordshire2.4
Solar Farm & Battery Energy Storagebattery storagebattery storage5approved, not builtupdated Dec 2025Jul 2024granted Oct 2025Dec 2025East Hertfordshire2.4
Westmill Quarry, Westmill Road Solar Farmsolar farmsolar farm7.3application submitted may be out of dateupdated Sep 2023Sep 2023—Sep 2023East Hertfordshire3.2
Welwyn Power Energy Storage Facilitybattery storagebattery storage5approved, not built may be out of dateupdated Jun 2022May 2022granted Aug 2022Jun 2022Welwyn Hatfield7.0
High Elms Lane Turbinewind turbinewind turbine2refusedupdated Mar 2012Jul 2011refused Oct 2011Mar 2012East Hertfordshire7.3
Broxbournebury Solar Fieldsolar farmsolar farm5permission expiredupdated Aug 2019Sep 2015granted Feb 2016Aug 2019Broxbourne7.6
Swangleys Farmsolar farmsolar farm8.5application withdrawnupdated Aug 2018Aug 2014—Aug 2018North Hertfordshire8.4
Stanborough, Hatfieldsolar farmsolar farm10approved, not builtupdated May 2025Aug 2023granted Sep 2024May 2025Welwyn Hatfield9.2
Stanborough, Hatfieldbattery storagebattery storage1.5approved, not builtupdated May 2025Aug 2023granted Sep 2024May 2025Welwyn Hatfield9.2
Benington Wind Farmwind farmwind farm6.8refusedupdated May 2009May 2008refused Jan 2009May 2009East Hertfordshire9.7
Smaller schemes under 1 MW, mostly rooftop solar (10)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
County Hallrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Mar 2022Feb 2022granted Apr 2022Mar 2022East Hertfordshire2.1
Stephen Austin & Sons, Caxton Hillrooftop solarrooftop solar0.3approved, not builtupdated Jun 2023Feb 2023granted Jun 2023Jun 2023East Hertfordshire2.4
Hertford Industrial Estate, Caxton Hillrooftop solarrooftop solar0.4application withdrawnupdated Aug 2024Jun 2024—Aug 2024East Hertfordshire2.5
Mercedes Benz Of Hertford, Foxholes Business Parkrooftop solarrooftop solar0.1approved, not builtupdated Mar 2023Feb 2023granted Mar 2023Mar 2023East Hertfordshire2.7
Ridgeway Academy, Herns Lanerooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Welwyn Hatfield5.8
Morrisons Supermarketrooftop solarrooftop solar0.3approved, not builtupdated Oct 2024Aug 2024granted Oct 2024Oct 2024Welwyn Hatfield5.9
Brownfieldsbattery storagebattery storage0.2approved, not builtupdated Oct 2023Aug 2023granted Sep 2023Oct 2023Welwyn Hatfield6.5
D W Windsor, Pindar Roadrooftop solarrooftop solar0.3abandonedupdated Jul 2024Dec 2023granted Jan 2024Jul 2024Broxbourne8.4
Fibron B X, Rd Parkrooftop solarrooftop solar0.7approved, not builtupdated Jul 2025May 2025granted Jul 2025Jul 2025Broxbourne9.1
Verge In Highway, Great North Roadbattery storagebattery storage0.2approved, not builtupdated Mar 2026Sep 2025granted Nov 2025Mar 2026Welwyn Hatfield9.4

Distance from the average position of the SG14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm5120041.3
Rooftop solar806001.8
Wind farm100010
Wind turbine100010
Battery storage5050011.9

MW in pipeline: pending, approved and under-construction capacity.

How East Hertfordshire decides solar, wind and battery applications

ApplicationsEast HertfordshireUK
Decided applications (solar, wind, battery)2010,236
Refused7 (35%)19%
Solar refused4 of 1312%
Onshore wind refused2 of 245%
Battery storage refused1 of 516%
Median time from submission to decision22.1 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in East Hertfordshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SG14, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.