Energy Projects Near You

Solar, wind and battery projects near Welwyn Garden City (AL7)

29 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of AL7 (Welwyn Hatfield): 2 are waiting for a planning decision, 22 approved but not yet running, 1 operational. The largest live scheme is Tollgate Farm Battery Storage (49.5 MW battery storage, under construction since 1 February 2022), 7.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

29projects within 10 km
2awaiting a decision
22approved, not running
1operational

Projects within 10 km of AL7

Projects of 1 MW and more (15)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Welwyn Power Energy Storage Facilitybattery storagebattery storage5approved, not built may be out of dateupdated Jun 2022May 2022granted Aug 2022Jun 2022Welwyn Hatfield0.9
Stanborough, Hatfieldsolar farmsolar farm10approved, not builtupdated May 2025Aug 2023granted Sep 2024May 2025Welwyn Hatfield2.9
Stanborough, Hatfieldbattery storagebattery storage1.5approved, not builtupdated May 2025Aug 2023granted Sep 2024May 2025Welwyn Hatfield2.9
Computacenter Warehouserooftop solarrooftop solar2under constructionupdated Nov 2019Jan 2019granted Mar 2019Nov 2019Welwyn Hatfield4.8
Gypsy Moth Avenuerooftop solarrooftop solar1.2approved, not built may be out of dateupdated Apr 2022Mar 2022granted Aug 2022Apr 2022Welwyn Hatfield4.9
Swangleys Farmsolar farmsolar farm8.5application withdrawnupdated Aug 2018Aug 2014—Aug 2018North Hertfordshire7.4
Dellsome Power Hatfield Grid Station Energy storage facilitybattery storagebattery storage5approved, not built may be out of dateupdated May 2021Apr 2021granted Jul 2021May 2021Welwyn Hatfield7.6
Tollgate Farm Battery Storagebattery storagebattery storage49.5under constructionupdated Feb 2022Oct 2017granted Jan 2019Feb 2022Welwyn Hatfield7.7
Tollgate Farm, Welham Green Solar Farmsolar farmsolar farm16application submittedupdated Sep 2025Jul 2025—Sep 2025Welwyn Hatfield8.0
Three Houses Lanesolar farmsolar farm11.3refusedupdated Feb 2017Sep 2014refused Oct 2016Feb 2017North Hertfordshire8.7
Solar Farm & Battery Energy Storagesolar farmsolar farm24approved, not builtupdated Dec 2025Jul 2024granted Oct 2025Dec 2025East Hertfordshire8.9
Solar Farm & Battery Energy Storagebattery storagebattery storage5approved, not builtupdated Dec 2025Jul 2024granted Oct 2025Dec 2025East Hertfordshire8.9
Westmill Quarry, Westmill Road Solar Farmsolar farmsolar farm7.3application submitted may be out of dateupdated Sep 2023Sep 2023—Sep 2023East Hertfordshire9.5
High Elms Lane Turbinewind turbinewind turbine2refusedupdated Mar 2012Jul 2011refused Oct 2011Mar 2012East Hertfordshire9.5
Potters Bar Solar Farmsolar farmsolar farm5operationalupdated May 2017Sep 2015granted Dec 2015May 2017Hertsmere9.8
Smaller schemes under 1 MW, mostly rooftop solar (14)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Morrisons Supermarketrooftop solarrooftop solar0.3approved, not builtupdated Oct 2024Aug 2024granted Oct 2024Oct 2024Welwyn Hatfield0.6
Brownfieldsbattery storagebattery storage0.2approved, not builtupdated Oct 2023Aug 2023granted Sep 2023Oct 2023Welwyn Hatfield0.8
Ridgeway Academy, Herns Lanerooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Welwyn Hatfield0.8
Verge In Highway, Great North Roadbattery storagebattery storage0.2approved, not builtupdated Mar 2026Sep 2025granted Nov 2025Mar 2026Welwyn Hatfield2.9
Welham Greenrooftop solarrooftop solar0.3approved, not builtupdated Jun 2022Jun 2022granted Aug 2022Jun 2022Welwyn Hatfield6.9
County Hallrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Mar 2022Feb 2022granted Apr 2022Mar 2022East Hertfordshire7.3
Stephen Austin & Sons, Caxton Hillrooftop solarrooftop solar0.3approved, not builtupdated Jun 2023Feb 2023granted Jun 2023Jun 2023East Hertfordshire8.4
Hertford Industrial Estate, Caxton Hillrooftop solarrooftop solar0.4application withdrawnupdated Aug 2024Jun 2024—Aug 2024East Hertfordshire8.5
Mercedes Benz Of Hertford, Foxholes Business Parkrooftop solarrooftop solar0.1approved, not builtupdated Mar 2023Feb 2023granted Mar 2023Mar 2023East Hertfordshire8.5
Sandringham school, The Ridgewayrooftop solarrooftop solar0.2approved, not builtupdated Jan 2024Oct 2023granted Dec 2023Jan 2024St Albans8.8
Queenswood School, Shepherds Wayrooftop solarrooftop solar0.2approved, not builtupdated Aug 2023May 2023granted Aug 2023Aug 2023Welwyn Hatfield9.2
North London Ad Plant, Coursers Roadrooftop solarrooftop solar0.2approved, not builtupdated Sep 2024Jul 2024granted Aug 2024Sep 2024Hertsmere9.8
Hatfield Roadrooftop solarrooftop solar0.3approved, not builtupdated Jan 2025Aug 2024granted Oct 2024Jan 2025St Albans9.9
Verulam Schoolrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Oct 2023granted Dec 2023Jan 2025St Albans10.0

Distance from the average position of the AL7 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm7221157.3
Rooftop solar14013005.5
Wind turbine100010
Battery storage7070066.4

MW in pipeline: pending, approved and under-construction capacity.

How Welwyn Hatfield decides solar, wind and battery applications

ApplicationsWelwyn HatfieldUK
Decided applications (solar, wind, battery)1510,236
Refused2 (13%)19%
Solar refused1 of 812%
Battery storage refused1 of 716%
Median time from submission to decision11.3 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Welwyn Hatfield

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near AL7, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.