Energy Projects Near You

Solar, wind and battery projects near Bury St Edmunds (IP30)

6 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IP30 (Mid Suffolk): 5 approved but not yet running, 1 operational. The largest live scheme is Valley Farm, Hessett (42 MW solar farm, approved on 23 March 2026, not yet built), 2.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6projects within 10 km
0awaiting a decision
5approved, not running
1operational

Projects within 10 km of IP30

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Valley Farm, Hessettsolar farmsolar farm42approved, not builtupdated Mar 2026Jun 2025granted Mar 2026Mar 2026Mid Suffolk2.3
Skyliner Wayrooftop solarrooftop solar1approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024West Suffolk7.1
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Mount Road & Prigmore Drive, Great Bartonbattery storagebattery storage0.2approved, not builtupdated Jun 2025Jul 2024granted May 2025Jun 2025West Suffolk7.6
Easlea Roadrooftop solarrooftop solar0.6operationalupdated Jan 2022Sep 2021granted Apr 2022Jan 2022West Suffolk7.9
Gainsborough Road Car Park Solar PV arraysrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Sep 2021Jun 2021granted Sep 2021Sep 2021Mid Suffolk9.2
E D F Energy, Barton Roadrooftop solarrooftop solar0.5approved, not builtupdated Feb 2023Dec 2022granted Jan 2023Feb 2023West Suffolk9.2

Distance from the average position of the IP30 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm1010042
Rooftop solar403101.7
Battery storage101000.2

MW in pipeline: pending, approved and under-construction capacity.

How Mid Suffolk decides solar, wind and battery applications

ApplicationsMid SuffolkUK
Decided applications (solar, wind, battery)3310,236
Refused5 (15%)19%
Solar refused3 of 1912%
Onshore wind refused1 of 245%
Battery storage refused1 of 1216%
Median time from submission to decision22.4 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

All projects in Mid Suffolk

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near IP30, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.