Energy Projects Near You

Solar, wind and battery projects near Ashaig (IV42)

1 solar, wind or battery project of 150 kW or more is recorded within 10 km of the centre of IV42 (Highland): 1 approved but not yet running. The largest live scheme is Feed Millakin (0.3 MW rooftop solar, approved on 18 July 2023, not yet built; REPD status may be out of date), 6.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

1projects within 10 km
0awaiting a decision
1approved, not running
0operational

Projects within 10 km of IV42

Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Feed Millakinrooftop solarrooftop solar0.3approved, not built may be out of dateupdated Jul 2023May 2023granted Jul 2023Jul 2023Highland6.4

Distance from the average position of the IV42 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar101000.3

MW in pipeline: pending, approved and under-construction capacity.

How Highland decides solar, wind and battery applications

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

All projects in Highland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near IV42, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.