Energy Projects Near You

Solar, wind and battery projects near Avoch (IV9)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of IV9 (Highland): 4 are waiting for a planning decision, 3 approved but not yet running. The largest live scheme is Wind Farm at 4.2 km west of Aviemore and 25 km south west of Inverness (133 MW wind farm, application submitted on 31 January 2025, no decision recorded), 9.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
4awaiting a decision
3approved, not running
0operational

Projects within 10 km of IV9

Projects of 1 MW and more (3)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Longman Landfill, Stadium Roadsolar farmsolar farm9.9application submittedupdated Mar 2026Mar 2026—Mar 2026Highland8.6
Wind Farm at 4.2 km west of Aviemore and 25 km south west of Invernesswind farmwind farm133application submittedupdated Apr 2025Jan 2025—Apr 2025Highland9.9
Highland Wind Farmbattery storagebattery storage30application submittedupdated Apr 2025Jan 2025—Apr 2025Highland9.9
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Raddery Smithy Solar PV System Installationsolar farmsolar farm0.1approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Highland4.2
Longman Pumping Station, Longman Drive - Photovoltaic Panelsrooftop solarrooftop solar0.7approved, not builtupdated Jul 2024Apr 2024granted Jun 2024Jul 2024Highland9.0
Shore Streetbattery storagebattery storage—approved, not builtupdated Jul 2025Dec 2024granted Jun 2025Jul 2025Highland9.6
Harbro Limited, Harbour Roadrooftop solarrooftop solar0.4application submitted may be out of dateupdated Feb 2023Jan 2023—Feb 2023Highland9.7

Distance from the average position of the IV9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm2110010.1
Rooftop solar211001
Wind farm11000133
Battery storage2110030

MW in pipeline: pending, approved and under-construction capacity.

How Highland decides solar, wind and battery applications

ApplicationsHighlandUK
Decided applications (solar, wind, battery)16010,236
Refused68 (42%)19%
Solar refused0 of 1512%
Onshore wind refused61 of 11445%
Battery storage refused7 of 3116%
Median time from submission to decision52.3 weeks17.0 weeks
Appeals lodged / allowed20 / 20—

All projects in Highland

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near IV9, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.