Energy Projects Near You

Solar, wind and battery projects near Market Rasen (LN8)

3 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LN8 (West Lindsey): 2 approved but not yet running. The largest live scheme is Barn Farm, Torrington Lane - Roof Mounted PV Solar system (0.1 MW rooftop solar, approved on 6 December 2024, not yet built), 8.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

3projects within 10 km
0awaiting a decision
2approved, not running
0operational

Projects within 10 km of LN8

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
RAF Faldingworthsolar farmsolar farm40permission expiredupdated Sep 2017Sep 2013granted Mar 2014Sep 2017West Lindsey8.4
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Barn Farm, Torrington Lane - Roof Mounted PV Solar systemrooftop solarrooftop solar0.1approved, not builtupdated Dec 2024Oct 2024granted Dec 2024Dec 2024East Lindsey8.6
Gulham Fields Poultry Unit, Gulham Roadrooftop solarrooftop solar—approved, not builtupdated Jul 2025Mar 2025granted Mar 2025Jul 2025West Lindsey9.7

Distance from the average position of the LN8 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm100000
Rooftop solar202000.1

MW in pipeline: pending, approved and under-construction capacity.

How West Lindsey decides solar, wind and battery applications

ApplicationsWest LindseyUK
Decided applications (solar, wind, battery)2610,236
Refused7 (27%)19%
Solar refused3 of 2112%
Onshore wind refused3 of 345%
Battery storage refused1 of 216%
Median time from submission to decision11.0 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

All projects in West Lindsey

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.