RAF Faldingworth (40 MW solar farm)

RAF Faldingworth is a 40 MW solar farm project in West Lindsey, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 31 March 2017; the record was last updated on 27 September 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
permission expiredstatus in REPD
27 September 2017record last updated
West Lindseycouncil area

Planning timeline

DateStage
23 September 2013Application submitted
31 March 2014Planning permission granted
31 March 2017Permission expired

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
permission expired
Record last updated
27 September 2017
Operator or applicant
Lunar Energy Power
Planning authority
West Lindsey
Planning application reference
130514
Site area
150.8 ha
Address (REPD)
Former RAF Faldingworth Spridlington Road Faldingworth Market Rasen
Council area (by location)
West Lindsey
Time to decision
27 weeks
REPD reference
2018

Who decides

ApplicationsWest LindseyUK
Decided applications (solar, wind, battery)2610,236
Refused7 (27%)19%
Solar refused3 of 2112%
Onshore wind refused3 of 345%
Battery storage refused1 of 216%
Median time from submission to decision11.0 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Highgate Lane, Normanby-By-Spital Solar Photovoltaic Farmsolar farm11approved, not built4.0
Stainton Oil Production Facilitywind farm28application withdrawn6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.355, -0.4476).